Project planning HOAI §34, LPH 5-9 for the construction project:
Extension and renewal of the surgical department of the hospital building with amb. Surgery and recumbent sick leave.
in several sections during operation.
Project planning HOAI §34, LPH 5-9 for the construction project:
Extension and renewal of the surgical department of the hospital building with amb. Surgery and recumbent sick leave.
in several sections during operation.
The funding decision is available. The realization takes place in construction phases and during ongoing operation. (see attached site plan and explanation report HU-Bau) The building application has been submitted. The approved net costs are: Kgr. 300 = EUR 3,924,400.00; Kgr. 400 = EUR 4,059,180.00; Kgr. 500 = EUR 304,750.00; Kgr. 600 = 491,850.00 EUR;
Kgr. 700 = EUR 2,735,000.00.