The object of the order is construction works consisting in the execution of works specified in the task under the name: Construction of a walkway in Skierbieszów Kolonia within the provincial road no. 843 Chełm—Kraśniczyn—Zamość from km 34+263 to km 34+587.
1. The detailed scope of material and quantities of works are set out in the attached object of works and the detailed technical specifications for the performance and acceptance of construction works.
2. The Contractor is obliged to ensure safe traffic and pedestrian conditions in the area of carried out works covered by the contract on the basis of a simplified design of the organisation of traffic (for the duration of the works carried out).
The object of the order is construction works consisting in the execution of works specified in the task under the name: Construction of a walkway in Skierbieszów Kolonia within the provincial road no. 843 Chełm—Kraśniczyn—Zamość from km 34+263 to km 34+587.
1. The detailed scope of material and quantities of works are set out in the attached object of works and the detailed technical specifications for the performance and acceptance of construction works.
2. The Contractor is obliged to ensure safe traffic and pedestrian conditions in the area of carried out works covered by the contract on the basis of a simplified design of the organisation of traffic (for the duration of the works carried out) approved by the Traffic Manager provincial.
3. Works shall be carried out in accordance with the following technical specifications:
4. General requirements for the Technical Specifications for the performance and acceptance of construction works and the Detailed Technical Specifications for:
Road industry:
1). Preparatory works:
1.1. measurement works for linear earthworks,
1.2. grubbing trunks,
1.3. removal of the layer of fertile land,
1.4. stripping of tubular culverts,
1.5. security of telecommunications cables,
1.6. protection of power cables;
2). earthworks:
2.1. earthworks carried out by excavators with transport of the scoop,
2.2. excavations and trenches performed transversely on the embankment;
3. Dehydration works:
3.1. excavations and excavations carried out for excavation by subtraction excavators,
3.2. interior-review wells of the indoor ditch;
4. Substructures:
4.1. profiling and compacting of the substrate under the structural layers of the pavement,
4.2. substructures of cement stabilized soil,
4.3. upgrade of the roadsides with broken aggregate;
5. Pavement:
5.1. paving of exits of concrete paving stones, 8 cm,
5.2. milling of bituminous pavement (old horizontal marking);
6. Finishing works:
6.1. sown of escarpments in the native land,
6.2. making insurance of slopes with openwork plates of the type “Lattice”,
6.3. reinforcement of the bottom of ditches and drainage elements from concrete elements,
6.4. tubular culverts under exits;
7). Traffic Safety Devices:
7.1. horizontal marking of the roadway,
7.2. segmental fences rigid slotted from steel pipes;
8). street elements:
8.1. concrete-lying curbs (indrives);
8.2. concrete fringes on a sand backing;