The purpose of this procurement is to contract a contractor to execute contract ‘M014 Security Doors’.
The contract includes:
— Security doors in accordance with. NS EN 1627 cl.3, cl.4 and cl.5
— Security gates in accordance with NS EN 1627 cl.3, cl.4 og cl.5
For a more detailed description of this contract's scope, refer to Part B Work Scope and Payment and Part F Drawings.
Optimalisation process.
After the contract has been signed there will be an optimalisation period of approx. 6 months in contract ‘M005 Internal construction work and technical installations’.
The aim of the optimalisation period is to:
1. Reduce the risk for the builder and contractor.
2. Provide optimal technical systems.
3. Ensure predictability and rational production.
4. Reduce project costs.
5. Create trust between the builder and contractor, team-building.
Contract ‘M014 Security Doors’, must reckon on participating in parts of this process for the coordination of progress and technical solutions.