Construction phase 1:
•330m² Creation of makeshift paths/storage areas
•3 pieces Manufacture of ramp constructions
•409.5 m erect and maintain/maintain construction fences
•Set up and keep 2 sanitary containers in place
•Set up, maintain and remove 2 pieces of mobile toilets
•12.00 m Creation of fall protection as a special protective measure in the course of the construction project
Construction phase 2.1:
•800m² Creation of makeshift paths and areas
•1 piece Manufacture of ramp constructions
•Make 3 running meters of pedestrian walkway covered
•Set up 200 linear metres of construction fences and maintain 90 linear metres of construction fences from construction phase 1
•Keep/maintain 2 sanitary containers from construction phase 1
•Set up, maintain and remove 2 pieces of mobile toilets
Construction phase 2.2:
•830m² of makeshift paths and areas
•2 pcs Manufacture of ramp constructions
•359.5 m of construction fences from construction phase 2.1
•2 sanitary containers from construction phase 2.1 are available/maintained
•Set up, maintain and dispose of 1 piece of mobile toilets
Construction phase 3.1:
•350m² of makeshift paths and areas
•2 pcs Manufacture of ramp constructions
•205 running metres of construction fences from construction phase 2.2
•2 sanitary containers from construction phase 2.2 are available/maintained
Construction phase 3.2:
•200m² of makeshift paths and areas
•2 pcs Manufacture of ramp constructions
•Set up 68.5 m of construction fences and 193.5 m of construction fences from construction phase 3.1
•2 sanitary containers from construction phase 3.1 are available/maintained
•Set up, maintain and dispose of 1 piece of mobile toilets
Construction phase 4.1:
•Create 210m² of makeshift paths and areas
•1 piece Manufacture of ramp constructions
•Set up 51 linear metres of construction fences and maintain 239 linear metres of construction fences from construction phase 3.2
•2 sanitary containers from construction phase 3.2 are available/maintained
•Set up, maintain and dispose of 1 piece of mobile toilets
•Demolition work (construction board)
Construction site equipment for the construction project Arberlanklinik Viechtach 4th construction phase over all construction phases.
Construction phase 1:
•330m² Creation of makeshift paths/storage areas
•3 pieces Manufacture of ramp constructions
•409.5 m erect and maintain/maintain construction fences
•Set up and keep 2 sanitary containers in place
•Set up, maintain and remove 2 pieces of mobile toilets
•12.00 m Creation of fall protection as a special protective measure in the course of the construction project
Construction phase 2.1:
•800m² Creation of makeshift paths and areas
•1 piece Manufacture of ramp constructions
•Make 3 running meters of pedestrian walkway covered
•Set up 200 linear metres of construction fences and maintain 90 linear metres of construction fences from construction phase 1
•Keep/maintain 2 sanitary containers from construction phase 1
•Set up, maintain and remove 2 pieces of mobile toilets
Construction phase 2.2:
•830m² of makeshift paths and areas
•2 pcs Manufacture of ramp constructions
•359.5 m of construction fences from construction phase 2.1
•2 sanitary containers from construction phase 2.1 are available/maintained
•Set up, maintain and dispose of 1 piece of mobile toilets
Construction phase 3.1:
•350m² of makeshift paths and areas
•2 pcs Manufacture of ramp constructions
•205 running metres of construction fences from construction phase 2.2
•2 sanitary containers from construction phase 2.2 are available/maintained
Construction phase 3.2:
•200m² of makeshift paths and areas
•2 pcs Manufacture of ramp constructions
•Set up 68.5 m of construction fences and 193.5 m of construction fences from construction phase 3.1
•2 sanitary containers from construction phase 3.1 are available/maintained
•Set up, maintain and dispose of 1 piece of mobile toilets
Construction phase 4.1:
•Create 210m² of makeshift paths and areas
•1 piece Manufacture of ramp constructions
•Set up 51 linear metres of construction fences and maintain 239 linear metres of construction fences from construction phase 3.2
•2 sanitary containers from construction phase 3.2 are available/maintained
•Set up, maintain and dispose of 1 piece of mobile toilets
•Demolition work (construction board)