Soil remediation, earthworks, water management, cleaning, disposal, reuse - Tank Farm Farge, Loading Station 2
LOT-0000
Soil Remediation Tank Farm Farge, Loading Station 2 - Federal.
Tender for soil remediation and earthworks, water management, cleaning, disposal/reuse at the former Tank Farm Farge, Loading Station 2
-1x Setup, operation, clearance of construction site facilities, including office containers
- Approx. 1,000 m² Construction, maintenance, and dismantling of access roads
- Approx. 15,050 m² Creation, maintenance of storage areas
- Approx. 11,000 m² Maintaining storage areas with non-remediation relevant material
- 1x Setup, operation, clearance of a black-and-white system
- Approx. 1300 m Fencing of the black area, erecting, maintaining, and clearing
- 1x Setup, clearance of groundwater management
- Approx. 48 days operating groundwater management
- 1x Prepare area for groundwater cleaning system
- 1x Set up, clear groundwater cleaning system
- Approx. 50 days operating groundwater cleaning system
- Earthworks under expert supervision
- Approx. 340 in-situ boreholes with sampling
- Approx. 540 composite samples prepared and sent to the lab
- Approx. 127,000 m³ dry excavation of soil up to 13 m above sea level and on-site preparation
- Approx. 35,400 m³ dry excavation of remediation relevant soil up to 13 m above sea level and
- Loading for soil cleaning
- 57 construction boxes (12m x 12m x 3m) at 13m above sea level to 16m above sea level
- Approx. 23,600 m³ wet excavation in the construction boxes and loading for soil cleaning
- Approx. 59,000 m³ remediation relevant excavation transported to suitable soil cleaning facility in gas-tight cover containers
- 186,000 m³ soil layered (max. 0.5m) backfill, static compaction
- 250 soil samples and analysis
- 40 ambient air accompanying measurements
- 3 dismantling of 2" and 5" groundwater measuring points