Drainage canal construction work | Tenderlake

Drainage canal construction work

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
16 July 2020
Closing Date:
16 September 2020
Location(s):
DE712 Frankfurt am Main, Kreisfreie Stadt (DE Germany/DEUTSCHLAND)
Description:
Wilhelmshöher Straße - Road and Civil Engineering Work [BL030]

Canal construction work, road construction work, construction work f. Pipelines, communication and power lines, work f. LSA.

Wilhelmshöher Straße is the main thoroughfare in the north-east Seckbach district in Frankfurt am Main.

It connects the Frankfurt boroughs of Bornheim, Seckbach and Bergen-Enkheim.

The construction project includes the fundamental renewal of the street areas of Wilhelmshöher Straße between Heinz-Herbert-Karry-Straße and Atzelbergstraße as well as the renewal of the canal, a traffic light system, the gas, water and electricity lines, the lighting systems and the renewal / addition of lines from Deutsche Telekom .

The section of road to be renovated extends to a length of approx. 530 m and approx. 11.50 m width and is to be implemented in 4 construction phases with sub-phases in the east-west direction.

Road construction - title 1:

- Asphalt break-up, e.g. T. contains approx. 3 450 m 2nd ;

- Break out asphalt construction with large paving z. T. contains approx. 1,400 m 2nd ;

- Asphalt break-up containing tar approx. 800 m 2nd ;

- Break up the concrete pavement approx. 2 150 m 2nd ;

- Break out curbs of all kinds. u. recycle about 1 100 m;

- Install street drain approx. 40 hours;

- Loosen soil and recycle / dispose of approx. 4,300 m 3rd ;

- Ballast base layer 0 / 32-0 / 45 mm, in different thicknesses 5 600 m 2nd ;

- Make asphalt superstructure approx. 3 100 m 2nd ;

- Create a semi-rigid covering layer HD 11, 5 cm approx. 400 m 2nd ;

- concrete curbs move approx. 1 100 m;

- Concrete paving u. - Lay tiles, walkway and driveways approx. 2,600 m 2nd .

Canal construction - title 2:

- Excavate and load the soil for individual trenches, shaft pits (L> 5), approx. 3,325 m 3rd ;

- Shoring trench and construction pits approx. 5 100 m 2nd ;

- demolition of sewer DN 300-500 approx. 255 m;

- Demolition of buildings approx. 5 hours;

- Partial demolition shaft approx. 4 hrs .;

- DN 400 (H) stoneware socket pipe in a single trench, approx. 530 m;

- Precast reinforced concrete shaft DN 1200 offset approx. 5 units;

- GRP shaft (UP-GF) DN1200 offset approx. 4 pieces;

- Move / manufacture combination shaft DN 1500 approx. 1 pc.

Cable line civil engineering work SVA - Title 3:

- Remove whip masts, drive off (SMP 30) approx. 3 hours;

- tear off cable protection pipes made of PVC-U up to 1 x 2 approx. 70 m;

- Pipe trenches, construction pits approx. 90 m 3rd ;

- Deliver and install junction boxes approx. 2 pieces;

- Deliver and install cable protection pipes up to 1 x 3 DN 100 approx. 25 m.

Pipeline construction gas / water - Title 4:

- BG / LG manuf., Depth up to 3.0 m approx. 600 m 3rd ;

- Build trench and construction pit shoring approx. 1 450 m 2nd ;

- PE-HD pipe laying up to d 225 approx. 1 150 m;

- Installation of slide valves and butterfly valves water approx. 19 pieces;

- Underfloor hydrants (W-HYD) approx. 7 hours;

- Water single-line house connection d63 approx. 34 units;

- Water - HA inspection / transferring / partial renewal approx. 26 hours;

- Gas - single-line house connection d63 approx. 17 units;

- Gas HA check / transfer / part renewal approx. 35 pieces

Power line construction - Title 5:

- BG / LG manuf., T up to 1.75 m approx. 740 m 3rd ;

- PEHD jacket pipes (protective pipes) d 125 approx. 1 900 m;

- Plastic jacket pipes (protective pipes) DN 120 to DN 150 approx. 1 900 m;

- Pipe trench and construction pit shoring approx. 80 m 2nd ;

- Cable laying cables up to> d 10 cm approx. 3 100 m;

- Cable disassembly cables up to> d 5.0 <= 10 cm 3 050 m;

- Disassemble cement pipes of all sizes approx. 1 150 m;

- Electricity single line house connection approx. 42 pieces

Line civil engineering street lighting - Title 6:

- BG / LG manuf., HoB B, t <= 1.25 m approx. 144 m;

- Plastic jacket pipes (protective pipes) d = 110 to d = 125 approx. 352 m;

- Cable laying cable <= d 2.5 cm approx. 1 300 m.

Line civil engineering Telekom - Title 7:

- Small buildings break off approx. 26 hours;

- KSCH type 1 cancel approx. 2 hours;

- Install KSCH Type 3 of 1.4 m approx. 1 pc .;

- Lay DN 110 pipes approx. 1 240 m;

- Unused and occupied KKF abort approx. 260 m;

- Lay out divided plastic pipes approx. 76 m.

Download full details as .pdf
The Buyer:
Stadt Frankfurt am Main
CPV Code(s):
45231000 - Construction work for pipelines, communication and power lines
45233121 - Main road construction works
45247112 - Drainage canal construction work