Roof waterproofing work and roof greening for the construction of a new triple gym
Main amounts:
- ca. 558 m2 Behelfsabdichtung G 200 DD
- approx. 1,615 m2 mineral wool insulation pitched roof
- approx. 558 m2 of foam glass insulation as slope insulation
Flat roof
- approx. 2,115 m2 of 2-layer bitumen railway roof waterproofing
- approx. 155 m connection roof waterproofing thermally insulated to
Rising components
- approx. 100 m connection roof waterproofing to roof superstructures
- approx. 95 m follow-up training roof waterproofing in the
Traufbereich
- approx. 78 m follow-up training roof waterproofing at the entrance
- approx. 500 m2 rolling gravel filling as a load
- approx. 1,615 m2 of extensive roof greening on pitched roof
- 3 pieces of roof light strips L approx. 29 m with SHEV wings
- 1 piece of roof light strip L approx. 3 m with NRWA wing
- 1 piece roof exit
- Rope safety system, approx. 39 anchor points, approx. 205
m Edelstahlseil
- approx. 122 m downpipe
- ca. 275 m Attikablechabdeckung
- ca. 78 m Dachrandabschlussprofil