Track, ceiling closure and stop construction work.
The construction project encompasses 3 construction areas which include demolition and new construction of track systems, ceiling and stop construction work.
Construction part 1:
Significant expansion work:
— 110.00 m joint cuts,
— 90.00 m
— 50.00 m
— 30.00 m highlands and lowlands (edge bricks, concrete shelves, L-shelves),
— 31.00 pieces of stop cover plates,
— 50.00 m
— 10.00 m
— 1.00 piece ZA with grooved rail as shear threshold siding with wooden sleepers in gravel bedding,
— 55.00 m NBS track,
— 20.00 m shear threshold with concrete sleepers,
— 200.00 t disposal of crushed stone,
— 30.00 st. concrete sleepers, dissipation to the BVG disposal company,
— 210.00 t disposal bitumen mixtures,
— 85.00 t concrete,
— 90.00 t disposal of soil and stone,
— 1.00 t plastics,
— 20.00 t iron and steel.
Essential installation work:
— produce 450.00 m
— 8.00 m
— 90.00 m
— 30.00 m thermowell DN 110,
— 300.00 m thermowell DN 63,
— Exchange 2.00 cable duct cover (KS II),
— 250,00 m
— 30.00 m
— 50,00 pieces of rail shock welds,
— 75.00 m NBS track,
— 62.00 m rail change 59R1 in the range KS 59R1 H60,
— 1.00 units ZA NBS track,
— 480.00 m
— 50.00 m
— 25.00 m high and low shelves (edge bricks, concrete shelves, L-shelves),
— 31.00 pieces of stop cover plates
Construction part 2:
Significant expansion services: '
— 245.00 m joint cuts,
— 200.00 m
— 145.00 m
— 265.00 m highlands and lowlands (edge bricks, concrete shelves, L-shelves),
— 32.00 pieces of stop cover plates,
— 450,00 m
— 125.00 m
— 41.00 m
— 103.00 m thermowells (DN20, DN48-63 and DN110),
— 1.00 units ZA NBS track,
— 1.00 pieces EA NBS track,
— 1.00 pieces IBW shear threshold glue with concrete sleepers,
— 40.00 m NBS track,
— 431.00 m shear threshold siding with concrete sleepers,
— 22.00 m shear threshold siding with wooden sleepers,
— 20.00 m grooved rail frame track with asphalt finish,
— 1,490.00 t crushed stone disposal,
— 650.00 concrete sleepers, dissipation to the BVG waste management company,
— 311.00 t disposal bitumen mixtures,
— 897.00 t concrete,
— 856,00 t disposal of soil and stone,
— 5.00 t plastics,
— 80.00 t iron and steel.
Essential installation work:
— produce 1,915.00 m
— 10.00 m
— 391.00 m
— 182.00 m
— 55,00 m thermowell DN 110,
— 504.00 m thermowell DN 63,
— 28.00 m thermowell NW 20,
— replace 3.00 cable duct cover (KS I and KS II),
— 8.00 pieces of underfloor lights,
— 2.00 pieces of sludge catcher shaft (rule sheet 410),
— 5.00 pieces of concrete drainage well,
— 300.00 m
— 180.00 m drainage pipe,
— 27.00 m
— 600.00 m
— 65.00 m
— 137.00 pieces of rail shock welds,
— 93.00 m NBS track,
— 40.00 m rail change in the existing NBS track (NBS 59R1 A 150),
— 120.00 m rail change 59R1 in the range KS 59R1 H60,
— 1.00 units ZA NBS track,
— 1.00 pieces EA NBS track,
— 1.00 pieces IBW shear threshold glue with concrete sleepers,
— 890.00 m
— 162.00 m
— 216.00 m high and low shelves (edge bricks, concrete shelves, L-shelves),
— 32.00 pieces of stop cover plates.
Construction part 3:
Significant expansion services: '
— 945.00 m joint cuts,
— 485.00 m
— 95.00 m
— 45.00 m high and low shelves (edge bricks, concrete shelves, L-shelves),
— 30.00 pieces of stop cover plates,
— 745.00 m
— 330.00 m
— 145.00 m
— 1.00 units ZA NBS track, both ZV as bituminous undercast frame track, entire ZA with asphalt cover,
— 1.00 units ZA as bituminous cast frame track with asphalt finish,
— 1.00 piece EW as bituminous cast frame track with asphalt finish,
— 45.00 m NBS track NBS 59R1 A 150,
— 14.00 m shear threshold siding with wooden sleepers KS 59R1 H60,
— 550.00 m grooved rail frame track with asphalt finish,
— 600.00 t disposal bitumen mixtures,
— 1,500.00 t concrete,
— 1 350.00 t disposal of soil and stone,
— 5.00 t plastics,
— 100.00 t iron and steel.
Essential installation work:
— produce 2 350.00 m
— 15.00 m
— 865.00 m
— 200.00 m thermowell DN 110,
— 1,000.00 m thermowell DN 63,
— replace 3.00 cable duct cover (KS I and KS II),
— 635.00 m
— 70,00 m
— 120.00 pieces of rail shock welds,
— 536.00 m NBS track,
— 15.00 m grooved rail frame track with asphalt finish,
— 12.00 m rail change in the existing NBS track (NBS 59R1 A 150),
— 44.00 m rail change 59R1 in the KS 59R1 H60range,
— 2.00 units ZA NBS track,
— 1.00 piece EW NBS track,
— 2 367.00 m
— 95.00 m
— 45.00 m high and low shelves (edge bricks, concrete shelves, L-shelves),
— 30.00 pieces of stop cover plates.