335 BENSZ - New school centre Bad Endorf
Create 5,800 m2 construction road and BE area
39 weeks open dewatering
5.840 m3 Baugrubenaushub
709 m3 Kieskoffer
520 m3 gravel box Workplan RSV columns
300 RSV columns
5,200 tons of humus layer disposal
9,300 tons of disposal of excavated material
910 m3 Hinterfüllarbeiten