Südfeldweg / P+R facility at Weststünnen station, new construction
The construction work includes the following works:
Road and sewer construction works and construction work on pipelines, telecommunications and power lines.
Von-Thünen-Straße/SüdfeldwegLot I
2,000 m3 of superstructure
Produce 7,500 m2 of frost protection layer
Producing 4,600 m2 of ballast base course
5,000 m2 of asphalt pavement
955 m Setting curbs
Produce 1,800 m of paving strips
Laying 4,300 m2 of concrete pavement
420 m installation of shoring
Laying 500 m of sewer DN 300/400
22 pcs Install street drains
Install 60 m angle retaining wall
54 pcs install bike racks
Verdistr./P+R-SüdLot II
850 m3 of excavated soil
1,100 m3 of superstructure
Produce 7,400 m2 of frost protection layer
Produce 5,300 m2 of ballast base course
4,300 m2 of asphalt pavement
1,040 m of curbs
1,375 m of paving strips
Laying 2,850 m2 of concrete pavement
Install 250 m2 shoring
Laying 230 m of sewer DN 300-500
Install 50 m angle retaining wall