Repainting.
Painting:
- Reinforced concrete ceilings 210 m
- Reinforced concrete walls 2 660 m
- Drywall ceilings 2,000 m
- Drywall 2,200 m
- Rework existing 300 m
- Floor coating 50 m
- Painting steel door frames 380 m,
- ETICS / external plaster 100 m
Events:
- start of service March 22, 2021,
- Sampling 13.1.2021,
- Completion total October 29, 2021.