New construction of the Lichtbergschule Eiterfeld, drywall work on the walls
The client is planning the construction of a new building for administration in Eiterfeld as part of the overall measure for the new construction of the Lichtberg School Eiterfeld, as an early partial construction measure of an existing 3-storey primary school building, which is being built in monolithic construction. The building block to be created is a very easily structured building mass.
Component: Cluster
Storey: 2 - 3 full storeys
Brief description of trade: drywall work walls cluster
Demolition of temporary walls approx. 180 sqm
Walls single stud 125 - 160 mm approx. 740 sqm
Sliding ceiling connections single-shell approx. 190 running metres
Door openings approx. 33 pcs.
Window openings 63.5 x 298 cm approx. 20 pcs.
Metal stud walls with cement building boards approx. 90 sqm
Double stud walls Installation walls approx. 360 sqm
Double stud walls classroom 28 cm approx. 620 sqm
Sliding ceiling connections double-skinned approx. 160 running metres
Facing shells approx. 180 sqm
Temporary walls New approx. 290 sqm
U-shaped supports approx. 25 x 25 x 325 cm approx. 28 pcs.
U-shaped supports approx. 25 x 25 x 220 cm approx. 50 pcs
Rohrverkleidungen ca. 50 lfdm
L-shaped cladding approx. 115 running metres
Inspection flaps sheet metal / GK approx. 75 pcs.