A4 - FBE AD Dresden-W - AS DD-Neustadt, FBE, lot 1 Earth and superstructure
1 Psch set up construction site
1 Psch construction office for AG
1 Psch Perform light-technical calculation
Remove 500 m³ of topsoil
Cover 4,800 m² of topsoil
Extend 5,000 m² trough
Produce 2,030 m crawler bed trough in concrete
Make a 320 m lawn trough
5,200 m² of soil loosening
Make 185 m² excavation pit
Establish 120 m pipe trench DN300
94 St Removing and replacing shaft parts
Remove 9 bays
8 pcs install plastic tray
Break off the 120 m drainage line
Produce 120 m plastic pipeline
18 pcs removing and installing parts of road drains
Carrying away 1700 m³ banquet
Produce 6,000 m of banquet
Produce 3,500 t of frost protection layer
49,000 m² asphalt milling 10 cm
Produce 47,500 m² of asphalt base layer AC 22 TS 24 cm
Produce 47,500 m² asphalt binder layer AC 16 BS 9 cm
4,500 m² of tie-down strips of low-noise mastic asphalt 3 cm produce 44,500 m² asphalt top layer from low-noise MA 8 S mastic asphalt.
640 m² asphalt surface layer made from low-noise MA 5 S mastic asphalt. Produce 10,500 m² of asphalt joint
3.00 m concrete ceiling cut 26 cm
Milling 45,000 m² concrete pavement 26 cm
100 m² building Pick up paving
100 m² building Making paving slabs
Pick up 225 m concrete shelves
Set 225 m concrete shelves
Remove the 60 m rail of the guard
Mount the 60 m rail of the protective device
10 St remove road sign
10 pcs set up the AG traffic sign
Produce 2 m² of foundation for road sign
Produce 50 m embankment stairs
Produce 10 m joint sealing on building
60 composite anchors to the building
Pick up and set 20 m of scuffing board on the cap
329 pcs steel beam HEB 260 5000 mm
30 pcs steel beams HEB 300 Shake 6150 mm
324 St Install precast reinforced concrete infill L = 2400 mm
28 St Install precast reinforced concrete infill L = 1900 mm
Install 900 m³ drainage concrete
1,500 m² facing shell made from LMB 10/60.
14 m³ gabion wall L x W x H 2.00 x 1.00 m manufactured