It is intended to fundamentally renew the section from junction (AS) Stukenbrock-Senne km 38,500 to the motorway junction (AK) Bielefeld km 45,900.
The following planning services must be performed:
Lot 1:
- Object planning traffic facilities, LP 5 + 6
- Object planning of civil engineering structures incl. noise protection walls, LP 1, 3, 6
- Structural planning Engineering structures incl. noise barriers, LP 2 + 3
Lot 2:
- Geotechnics for the new construction of the noise barriers
Planning services for traffic facilities and bridge structures including noise protection wallsOP traffic facilities:
The contractor (contractor) assumes the execution planning according to work phase 5 as well as the preparation of the award according to LPH 6 of the HOAI for the object planning of traffic facilities. The basis is a design plan. Due to adjustments, the Contractor is additionally granted positions from LPH 1 and LPH 3 of the HOAI.
OP civil engineering structures:
The contractor (contractor) assumes the basic determination according to performance phase 1, as well as the design planning according to work phase 3 and the preparation of the award according to LPH 6 of the HOAI for the object planning of civil engineering structures.
FP Structural Design:
The contractor (contractor) takes over the preliminary planning according to work phase 2, as well as the design planning according to work phase 3 of the HOAI for the specialist planning structural design.
Geotechnical engineeringThe contractor (contractor) is responsible for the preparation of a geotechnical report for the new foundation of the noise barriers.