Rosny-Sous-Bois railway station is on the line from Paris-Est to Mulhouse, it is located in the Seine Saint-Denis department. It is served by Line E, at kilometre point (PK) 12.631.
The footbridge of the Rosny-sous-Bois station was built in 1912.
The scope of the operation extends over the entire historic footbridge:
Refurbishment of the footbridge, which includes asbestos removal and lead removal. Removal of the asbestos deck and the footbridge cover, followed by the installation of a new deck and a new roof.
Installation of architectural enhancement lighting. Removal and reinstallation of the two stairs towards the platforms and the 2 stairs that give access to the footbridge.
Possible additional benefit:
Refurbishment of the quay shelters including the removal of leads, the removal of roofs and the installation of new roofs.
The works, studies and supplies to be carried out by the Company are detailed, where applicable, in the descriptive notes or in the CCTP annexed to this contract and in the various documents of the contract.
They are divided into several bodies of states:
- Construction site installation - scaffolding
- Decontamination, demolition
- Steel structure – Structural work – Painting
- Locksmith - Painting
- Roofing-Carpentry-Painting
-CFO-CFA