Description:
Upgrading, 3 Tunnels in Årdal

The Steggja tunnel is 1 549 metre long. A breakdown bay must be blasted with an accompanying niche for a technical building. Trenches must be excavated on both side of the tunnel for electrical installations and a flushing water pipe with sand traps.

The Finnsås tunnel is 2 412 metre long. 2 breakdown bays must be blasted with accompanying niches for technical buildings. Trenches must be excavated on both side of the tunnel for electrical installations and a flushing water pipe with sand traps.

The Kolnos tunnel is 658 metre long. A breakdown bay must be blasted with an accompanying niche for technical building. Trenches must be excavated on both side of the tunnel for electrical installations and a flushing water pipe with sand traps.

The Steggja tunnel is 1 549 metre long. A breakdown bay must be blasted with an accompanying niche for a technical building. Trenches must be excavated on both side of the tunnel for electrical installations and a flushing water pipe with sand traps.

Main quantities:

— the demolition and removal of the current PE foam,

— blasting works for breakdown bays,

— blasting works for niches for technical buildings,

— the delivery of new technical buildings,

— blasting works for new emergency stations,

— new water/frost protection work,

— trenches on both sides of the tunnels,

— the delivery and installation of a prefabricated cable duct including manholes,

— new flushing water pipes with sandtraps.

The Finnsås tunnel is 2 412 metre long. Two breakdown bays must be blasted with accompanying niches for technical buildings. Trenches must be excavated on both side of the tunnel for electrical installations and a flushing water pipe with sand traps.

Main quantities:

— the demolition and removal of the current PE foam,

— blasting works for breakdown bays,

— blasting works for niches for technical buildings,

— the delivery of new technical buildings,

— blasting works for new emergency stations,

— new water/frost protection work,

— trenches on both sides of the tunnels,

— the delivery and installation of a prefabricated cable duct including manholes,

— new flushing water pipes with sandtraps.

The Kolnos tunnel is 658 metre long. A breakdown bay must be blasted with an accompanying niche for technical building. Trenches must be excavated on both side of the tunnel for electrical installations and a flushing water pipe with sand traps.

Main quantities:

— the demolition and removal of the current PE foam,

— blasting works for breakdown bays,

— blasting works for niches for technical buildings,

— the delivery of new technical buildings,

— blasting works for new emergency stations,

— new water/frost protection work,

— trenches on both sides of the tunnels,

— the delivery and installation of a prefabricated cable duct including manholes,

— new flushing water pipes with sandtraps.

Download full details as .pdf
The Buyer:
Statens vegvesen region vest
CPV Code(s):
45000000 - Construction work