Installation of doors (wood) in the existing building (cultural monument)
4 pcs Delivery, preparatory work & new installation of glass partition wall incl. portal door made of glass elements, inside
3 pcs Delivery, preparatory work & reassembly of arched element incl. sash with glass elements, side panels and skylight, exterior
The execution of the work is expected to take about 6 weeks with a work interruption of about 12 weeks.
Due to complex dependencies, continuous processing cannot be assumed.
Start: 11 week 2024
End: CW 28, 2024
Single deadlines:
Preparatory work 11th week - 12th week 2024
Main work 25th week – 28th week 2024