The contract includes the delivery of items for a MMV mixed-mix mixed flow pilot plant.
The division takes place in 2 lots:
- Lot 1: control,
- Lot 2: charger.
Control MMP requirements:
- control - operating unit (room A),
- Control - control cabinet (room B),
Provided connecting lines (room A <-> room B),
- 2 x 12 G 1.5 mm
- 2 x singlemode fiber optic duplex, plug type SC,
- 2 x multimode fiber optic duplex, type SC connector.
Requirements for the capacitor charger:
- voltage: 0 - 20 kV positive (adjustable),
- charging power: 12 kJ / s - short-term peak power: 20 kW,
- programming and monitoring: 0 - 10 V for voltage and current,
- Power input: 3x 400 VAC, 47 - 63 Hz,
- Output: Plug-in HV cable, 3 m, 2nd end open,
Possibility to connect several chargers in parallel,
- Profibus interface.