"Integrated contract" Works for the construction of the 380 kV Chiaramonte Gulfi – Ciminna power line (two lots cannot be combined)
"Integrated contract" Works for the construction of the 380 kV Chiaramonte Gulfi – Ciminna power lineExecution design and construction of a 380 kV overhead power line in double terna for the connection of the existing power stations of Chiaramonte Gulfi and Ciminna relating to lot 1 (section 1 + section 2):
Section 1: from the portal of the SE Chiaramonte to support n. 59 (length about 24.6km)
Strand 2: from support 60 to support no. 119 (length approx. 24.7km)
"Integrated contract" Works for the construction of the 380 kV Chiaramonte Gulfi – Ciminna power lineImplementation and construction of a 380 kV overhead power line in double terna for the connection of the existing power stations of Chiaramonte Gulfi and Ciminna relating to lot 2 (section 3 + section 4):
Strand 3: from support 120 to support no. 173 (length approx. 23km)
Strand 4: from support no. 174 to support no. 223 (length approx. 20.8km)