New technical + structural equipment for industrial waste heat utilisation/district heating feed-in

Stadtwerke Düsseldorf AG (SWD) operates a biomass power plant at the Garath site, which also supplies the Benrath network via an existing district heating transport pipeline. In the future, SWD plans to be able to supply the Benrath and Garath island grids with waste heat and CHP heat via Henkel AG's industrial site in Düsseldorf-Holthausen.

The waste and CHP heat is taken from the following two sources:

- CHP heat from a 4.8 bar process steam rail by means of heating condensers (2 x 15 MWth)

- Waste heat from an exhaust gas heat exchanger (AWÜ, 4.5 MWth), which uses the residual heat from the boiler 2 and gas turbine generation rails and thus improves the energy efficiency of the power plant.

The object of the contract is the construction of a building and the construction and commissioning of the plant and I&C technology for the energy center, the chimney including exhaust gas heat exchanger and the connecting piping systems.

The contractor shall only be commissioned if the competent bodies of SWD agree to the order described here. If the committee approval is refused, the contractor may not assert any claims, in particular no claims for damages, against the Client.

Energy centre (building incl. plant and I&C technology as well as chimney with exhaust gas heat exchanger)

As part of the supplies and services to be provided in Lot 1, a new building (energy centre) is to be constructed and the following plant components installed:

- Energy centre building (approx. 25 m x 27.5 m x 11.96 m (L x W x H))

o Gross floor area approx. 690 m²;

o Converted room approx. 6,500 m³

o Earthworks and drainage works

o Foundation + sole etc.

o Supporting structure made of precast reinforced concrete elements

the Stahlbauarbeiten

o Roof and façade work

o Windows + gates + doors

o Screed and tile work

o Painting work

- 2 x heating condensers (steam/hot water) with 15 MWth each

- 2 x heat exchangers (hot water/hot water) with a total of 4.5 MWth

- Mains pumps (3 x 50%) for decoupling the heat into the district heating network of Stadtwerke Düsseldorf

- Generator pumps (8 pieces)

- 2 pressure maintenance for heating water and coupling circuit

- Condensate system (condensate tanks and pumps)

- Steam system (DN 500 and smaller)

- Piping technology (DN 350 and smaller)

- steelwork

- I&C technology (transformers. Medium-voltage switchgear, low-voltage main distribution board)

- Control room for maintenance operations (no permanent workstation)

- Heat storage tank with 50 m³ (expansion option)

- ventilation systems

In addition, the exhaust gas heat exchanger in combination with a new chimney forms an essential part of this batch. With this, the previously unused exhaust gas heat is made usable all year round for the heat supply of SW Düsseldorf. The following system components must be installed:

- New steel chimney with a height of 48.7 m and a diameter of 3.0 m

- Flue gas heat exchanger with 4.5 MWth (installation in exhaust pipe)

- Abgasleitung

- Piping technology

- I&C technology (power supply, control technology, safety devices, assembly)

- Chimney and heat exchanger foundation

Rohrleitungstrassen

The heat sources are connected via pipelines that are laid on pipe bridges. These are "merely" used for heat transport. Control engineering operations do not take place in this section.

Scope of delivery and services:

- Steam pipe DN 500 (approx. 100 m) incl. integration into the stock via T-piece and double shut-off (option)

- HW cable coupling circuit DN 250 (approx. 1,000m)

- Kondensatleitung DN 125 (ca. 500 m)

Download full details as .pdf
The Buyer:
Stadtwerke Düsseldorf AG
CPV Code(s):
45210000 - Building construction work
45230000 - Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork
45350000 - Mechanical installations
45351000 - Mechanical engineering installation works