General renovation of the east wing of the HIP secondary school in Calw:
The east wing of the Heinrich Perrot secondary school in Calw is the last building of the school complex in the city centre, which
has not yet undergone a general renovation. For this purpose, the entire east wing will be cleared. And the
The school moves into additional space in the west wing and in the neighboring schools, as well as in containers that have yet to be set up in the schoolyard of the neighboring Hermann Hesse Gymnasium. The refurbishment includes all four
Floors of the east wing.
It is planned to start the work in November 2023 with the demolition work and after about 18 months
in May 2025.
Heating equipment:
Disassembly approx. 70 pcs link + plate HKs with consoles
Dismantling approx. 750 m of heating pipeline
Dismantling 1 pc. heating manifold incl. 5 pcs. outlet groups
Conversion work in the existing heating distribution room
1 pcs. heating manifold with 5 outlet groups
Connection of approx. 40 HVAC units (parapet + ceiling units)
approx. 38 radiators
approx. 1,800 m pipeline with insulation
approx. 100 fire protection bushings
approx. 50 core drillings