The purpose of the contract is to select one or more electricity suppliers for the SEBES Medium Voltage (MT), Low Voltage (BT) sites. The contract is divided into lots that can be awarded individually፦ Lot 1: supply of electricity to the “main” site (65 kV). Next to the current station, the new water generation station is being gradually commissioned and is part of Lot 1. - Lot 2: supply of electricity to the “backup solutions” sites (20 kV). - Lot 3: supply of electricity to the “valve chambers” sites (20 kV and BT).
Lot 1: supply of electricity to the “main” site (65 kV)Lot 1: supply of electricity to the “main” site (65 kV). Next to the current station, the new water production station is being gradually commissioned and is part of Batch 1.
Lot 2: supply of electricity to “backup solutions” sites (20 kV).Lot 2: supply of electricity to “backup solutions” sites (20 kV).
Lot 3: supply of electricity to the “valve chambers” sites (20 kV and BT).Lot 3: supply of electricity to the “valve chambers” sites (20 kV and BT).