St. Marienwörth Hospital
Renovation of the bed house in component A to C
level +3
Gewerk electrical systems.
3rd floor in the bed house in St. Marienwörth hospital,
Parts A, B, C and D are being rehabilitated. The remediation measure
It is divided into 3 construction phases (near BT D, near side — city side BT A-C).
— 1st BA, part D near side: access and neonatal ward,
— 2nd BA, nearby: 7 bed rooms and function rooms,
— 3rd BA, city side: 11 bed rooms and function rooms.
During the 1st construction phase, an early measure (fire protection and access for the new supply lines) is implemented in component D.
The overall measure is estimated to have a construction period of around 24 months.
Surrounding floors and components are in operation.
The call for tenders includes the above construction phases.
Estimated execution dates:
1.BA, part D access and neonatal ward
Complete installation: approx. September 2021 to around February 2022
2.BA, close-up
Rough installation: about February 2022 to April 2023
Fine installation: about July 2023 to October 2023
3.BA, city side
Rough installation: about January 2024 to March 2024
Fine installation: about June 2024 to about September 2024
low voltage installation systems
— distributions, AV, SV; 5 pieces,
— cable and line system; approx. 32,000 m,
— devices, approx. 720 pieces.
lighting systems
— About 280 pieces
Medical and laboratory equipment
— 54 beds, 18 media tracks.
Other titles:
— high voltage system, other
- TV and antenna system,
— time service systems, watch systems,
— automation systems (EIB),
— recycling, interim landfilling and disposal
— Provisional technical installations.