St. Marien and Annastifts Hospital
Future project human + health
Adding component G and converting component F
Gewerk VE_502 outdoor facilities - landscaping
Approx. 590 m³ drainage duct work with
approx. 336 linear metres of piping ditches, drainage lines,
8 drainage inspection shafts incl. excavation pit
approx. 2,210 m³ excavation trench infiltration plant and feed structures
Approx. 145 running meters above ground rainwater drainage devices such as gutters, drains, etc. approx. 9 pcs
Drainage pipelines and shafts as well as optical sewer testing
Approx. 560 m³ earthworks
Approx. 1,600 tonnes of soil disposal
Approx. 93 linear meters of staircases
53 metre retaining walls made of prefabricated parts with heights of 0.75 m to approx. 2.50 m as wheelchair ramp system main entrance
55 linear metre retaining walls made of prefabricated parts with a height of up to 2.80 m
Approximately 1,350 m² of pathways, driveways fire brigade paving areas made of concrete stone/grass paving stone
vegetation work including plant delivery and planting/sowing approx. 29 trees/80 m hedge
Planting areas/lawns including finishing care 960/200 m²
Approx. 230 linear meters steel construction work railings/fall arres/handrails
equipment such as bollards, signs, bicycle parking
Outdoor lighting including ditches and cable pull 240 m³/2300 m
Wall lights/bollard lights/mast lights 20 pcs /13 pcs/9 pcs
Start of construction: probably 24/25 week 2022
Completion: construction facilities within 234 working days, by the end of 11th week 2023 at the latest
Planting at the latest end of week 15, 2023
The work is divided into several sections/sub-areas.