Reconstruction of the existing power connection built under the building permit No. 1880p/2019 of December 3, 2019, consisting in the execution of construction works related to the foundation and integration of the electricity storage with the photovoltaic farm and with the existing energy consumption systems of the Mazovian Provincial Hospital Drewnica Sp. z o.o. The contract includes the execution of complete construction and executive documentation, delivery, installation and commissioning of the electricity storage system. This task is aimed at using the surplus energy available for personal use.
The contract includes the supply of electricity storage with integration with a photovoltaic farm and existing energy consumption systems and consists m.in:
1) conducting the necessary formal and legal procedures and obtaining the required consents, permits, provisions or administrative decisions,
2) preparation of design documentation for the task covering construction projects in the power industry in the field of installation of an electricity storage system from the installation
photovoltaic and connecting it to the existing power infrastructure and PV installation, together with the required executive documentation,
3) development of technical specifications for the execution and acceptance of works,
4) installation of the installation of an electricity storage system from a photovoltaic installation and connecting it to the existing power infrastructure and PV installation,
5) implementation of the material and financial schedule for the installation of the installation of an electricity storage system from a photovoltaic installation and connecting it to the existing power infrastructure and PV installation,
6) integration with the existing Building Management System
7) purchase of necessary components, materials and delivery,
8) execution of the necessary construction and installation works,
9) execution and delivery of as-built documentation necessary for the proper use of the installation by users,
10) commissioning of built-in devices and installations,
11) obtaining by the Investment Contractor all decisions and permits and making notifications and arrangements necessary to allow the Investment to be used
12) making the necessary training for the service.
A detailed description of the subject of the contract, including the parameters of the investment task and details of technical solutions, is included in the Functional and Utility Program constituting Annex No. 8 to SWZ.