Renovation of the surface of national roads divided into 3 parts: part 1 - expressway No. S52b, part 2 - expressway No. S1g and A4 motorway, part 3 - expressway No. S86

The subject of the Order is:

Renovation of the surface of national roads divided into 3 parts: part 1 - expressway No. S52b, part 2 - expressway No. S1g and motorway A4, part 3 - expressway No. S86.

The Contracting Authority allows the submission of partial tenders. The contractor may submit a bid for one, click or all parts of the contract.

The performance of the contract is subject to Polish law, including in particular the Construction Law, the Civil Code and the Public Procurement Law.

The Contractor will be obliged to perform construction works in accordance with Polish law, in particular with technical and construction regulations, regulations on independent technical functions in construction and regulations regarding products, materials used in construction.

The subject of the order is described in detail in Volumes III - V SWZ.

expressway No. S52b

The scope of the contract for part 1 of the contract includes:

(a) section. S52b from km 0+000 to km 5+500 carriageway right /m. Cieszyn/;

• Cold milling of surfaces;

• Surface cleaning;

• Surface sprinkling;

• Execution of a layer of asphalt concrete AC 22W thickness 10 cm;

• Execution of a binding layer of asphalt concrete AC 16W thickness 8 cm;

• Making an abrasion layer from the SMA mixture - thickness 4 cm;

• Local exchange of wastewater from precast concrete elements and concrete curbs;

• Replenishment of understated roadsides;

• Restoration of road markings.

(b) section. S52b from km 11+800 to km 15+927 right and left carriageway /Międzyświeć – Pogórze/ excluding sections from km 12+800 to 13+200 bridge over the Bładnica River on the left carriageway:

• Cold milling of surfaces;

• Surface cleaning;

• Surface sprinkling;

• Execution of a layer of asphalt concrete AC 22W thickness 10 cm;

• Execution of a binding layer of asphalt concrete AC 16W thickness 8 cm;

• Making an abrasion layer from the SMA mixture - thickness 4 cm;

• Reconstruction of bituminous expansion joints on bridge structures;

• Adjustment of grilles and inspection manholes;

• Local exchange of wastewater from precast concrete elements and concrete curbs;

• Replenishment of understated roadsides;

• Restoration of road markings.

(c) section. S52b from km 15+927 to km 19+900 left carriageway /Pogórze – Grodziec/:

• Cold milling of surfaces;

• Surface cleaning;

• Surface sprinkling;

• Execution of a layer of asphalt concrete AC 22W thickness 10 cm;

• Execution of a binding layer of asphalt concrete AC 16W thickness 8 cm;

• Making an abrasion layer from the SMA mixture - thickness 4 cm;

• Reconstruction of bituminous expansion joints on bridge structures;

• Adjustment of grilles and inspection manholes;

• Local exchange of wastewater from precast concrete elements and concrete curbs;

• Replenishment of understated roadsides;

• Restoration of road markings.

expressway No. S1g and motorway A4

The scope of the contract for part 2 of the contract includes:

(a) section. S1g from km 0+000 to km 5+645 /Kamesznica – Laliki/:

• Cold milling of surfaces;

• Surface cleaning;

• Surface sprinkling;

• Execution of a substructure layer of asphalt concrete AC 22W

gr. 10 cm;

• Execution of a binding layer of asphalt concrete AC 16W thickness 8 cm;

• Making an abrasion layer from the SMA mixture - thickness 4 cm;

• Reconstruction of bituminous expansion joints on bridge structures;

• Adjustment of grilles and inspection manholes;

• Local exchange of wastewater from precast concrete elements and concrete curbs;

• Replenishment of understated roadsides;

• Restoration of road markings;

(b) section. A4 from km 335+980 to km 337+000 roadway collecting - distributing rights / m. Katowice/:

• Cold milling of surfaces;

• Surface cleaning;

• Surface sprinkling;

• Execution of a substructure layer of asphalt concrete AC 22W

gr. 10 cm;

• Execution of a binding layer of asphalt concrete AC 16W thickness 8 cm;

• Making an abrasion layer from the SMA mixture - thickness 4 cm;

• Adjustment of grilles and inspection manholes;

• Local exchange of wastewater from precast concrete elements and concrete curbs;

• Restoration of road markings.

expressway No. S86

The scope of the contract for part 3 of the contract includes:

(a) section. S86 from km 18+030 to km 23+954 right and left carriageway

/ Sosnowiec – Katowice/:

• Cold milling of surfaces;

• Surface cleaning;

• Surface sprinkling;

• Execution of a layer of asphalt concrete AC 22W thickness 10 cm;

• Execution of a binding layer of asphalt concrete AC 16W thickness 8 cm;

• Making an abrasion layer from the SMA mixture - thickness 4 cm;

• Reconstruction of bituminous expansion joints on bridge structures;

• Adjustment of grilles and inspection manholes;

• Local exchange of wastewater from precast concrete elements and concrete curbs;

• Replenishment of understated roadsides and felling of inflated roadsides;

• Restoration of road markings.

Download full details as .pdf
The Buyer:
Generalna Dyrekcja Dróg Krajowych i Autostrad Oddział w Katowicach
CPV Code(s):
45233140 - Roadworks
45233220 - Surface work for roads
45233221 - Road-surface painting work
45233223 - Carriageway resurfacing works