The contract mainly consists of the construction of approx. 1 800m new road and upgrades to approx. 300m old road. Parts of the route go through a high cutting, approx. 450m and there are also two short marsh areas. Approx. 200m of foot/cycle path shall be developed. Ditches shall be excavated and cables laid for Finnås Kraftlag, approx. 2 400m and approx. 700m street lights for the Norwegian Public Roads Administration. Noise reduction screens shall be built around parts of the old cemetery by the road.
Main amounts: Blasting and removal of stones approx. 112 000 m³, earth/marsh matter approx. 50 000 m³, securing rock/bolts approx. 1 500 pcs, asphalt approx. 17 500 m³ (5,250 tons).