Basic renovation of the office building
Construction site traffic areas/early measures:
1390 m3 Soil excavation/soil removal
230 m Kabellehrrohre
3 St Kabelzugschächte
6 m3 dismantling of massive existing light wells
30 m2 dismantling external waterproofing
20 m dismantling of drainage pipe and 3 inspection shafts
6 pcs core drilling, diam. up to 200mm, natural stone basement exterior wall
D up to 115 cm
6 casing flange plates up to DN 250
100 m2 concrete facing shell reinforced, W 15 cm
165 m2 exterior wall waterproofing with 2K thick coating
165 m2 Perimeterdämmung Kelleraußenwand 80-100 mm
1 pc precast concrete shaft U-light shaft, impermeable to water
483 tons of building backfill frost protection 0/45
1050 m3 base course for construction site traffic area, frost protection 0/45
1500 m2 Geogitter- Vliesstoffkombination
10 St Lastplattendruckversuche
15 St Control Test Base Layer Deformation Module
74 m parking concrete shelf HB 15/30
5 pcs: Maintenance services, base course, BE surfaces, incl. material delivery