The district of Neuburg-Schrobenhausen intends to expand the grammar school in Schrobenhausen again and to renovate the aging existing building from the ground up. These measures will be carried out in two construction phases. In the following, the construction phase II will be put out to tender. After completion of the BAII, the BAIII will be put out to tender.
The following measures are planned for the conversion, renovation and expansion of the grammar school in BA II:
- New construction of a classroom wing
- Energy-efficient upgrading of the existing façade
- Dismantling of the existing gable roof
- Construction of a continuous roof for the existing building and new construction
- Renewal and energetic upgrading of windows / facades
- Construction of a circumferential escape balcony on level 1 and level 2
- Upgrading of existing building services
- Measures for fire protection upgrading
The plot has a cumulative size of approximately 16.500m2.
External dimensions of the new building:
Length: approx. 40,00m
Width: approx. 25,00m
Height: approx. 12.30m from OK FFB basement
External dimensions of the portfolio in the area of the BAII (renovation area): Largest length: approx. 45.30m
Largest width: approx. 22,00m
Maximum height: approx. 12.70m from OK FFB basement
Construction of new construction:
The classroom wing will be built in solid reinforced concrete. The statically necessary interior walls are made of reinforced concrete in fair-faced concrete quality. Facing shells and subordinate walls are created in lightweight construction (drywall). The ceiling above the 1st floor is sealed bituminously and provided with a two-layer insulation layer. A carpenter's hipped roof construction is erected. The hipped roof is covered as an aluminium crimped seam roof.
The concrete structure is insulated by means of a rear-ventilated curtain wall.
builderThe 1 - Baumeister- 05A
Demolition work in stock:
- Demolition of stairs and floor slab approx. 25m3
- Demolition of roof truss with tiled roof tile roofing 215 m2
- Shell construction:
- In-situ concrete of walls and ceilings 1,450 m3
- Waterproofing and insulation in the ground 345 m2
- Formwork of wall and ceiling surfaces 4.200m2 Fair-faced concrete wall formwork 1.400m2
- Structural steel of bars and mats 190t
- Stocking of concrete surfaces 150m2
scaffolding workLot 2 - Scaffolding 07B:
Scaffolding work:
- Working scaffolding for façade work LK 3, W09
- 2,100m2 scaffolding work for new construction and existing buildings
- Retention for approx. 56 weeks
- Version with brackets and internal railings
Demolition work in existing buildingsLot 3- Demolition work in stock 05C:
Demolition work in stock:
- Demolition of floor covering made of linoleum sheets = 975m2
- Demolition of non-protruding interior masonry = 35 m3
- Demolition of non-trahenden exterior masonry (parapet) = 34m3 Demolition of GK suspended ceilings = 1,230 m2
- Demolition of plaster containing asbestos = 110 m2
- Demolition of doors with steel frames, lead-containing lacquer = 15 pieces
earthworkLot 4 - Earthworks- 05D
Demolition work in the outdoor facilities and excavation of the excavation pit
Preliminary measure:
- Demolition work of paved areas and green zones Expansion of paved areas with substructure = 1,300 m2
- Dismantling concrete steps = 115m
- Demolition of retaining wall=21m3
- Demolition of reinforced concrete floor slab = 65 m3
- Excavated earth Bkl. 3-5= 7,120 m3
- Planie of the excavation pit= 2,350 m2
site equipmentLot 5 - Construction site equipment 05E:
Delivery, provision and removal of construction site equipment services:
Site equipment:
- 65 m construction fence with 2nd flg. Gate system
- 1 St. WC Container