Bridge renewal construction work

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
02 October 2018
Closing Date:
22 October 2018
Location(s):
DEA15 Mönchengladbach, Kreisfreie Stadt (DE Germany/DEUTSCHLAND)
Description:

Lot 1: BW 1006 Bridge An der Holter Sportstätten;

Lot 2: BW1002 bridge railway;

Lot 3: BW 1010 Viersener Straße bridge; BW 1008 bridge Lindenstraße; BW 1009 bridge Haiderfeldstraße.

BW 1006 Bridge At the Holter sports facilities

New superstructure and repair of existing abutments

It is at the bridge to a road overpass, which leads over an electrified railway line. During construction, the route is out of service.

Inventory from 1910

Superstructure of rolled sections with filled concrete (vault)

Existing width 8.20 m, total length 9 m.

Planned new building superstructure

Rolled beams in concrete

Width 13.50 m, total length 9 m

Repair of masonry abutments (masonry restoration)

Work superstructure

Dismantling of the caps with guardrails and guards.

Removing the individual coating layers.

Expansion of the superstructure.

Dismantling of the upper abutment areas.

Production of the new support benches including the rear spurs and wings.

Production of the new superstructure.

Preparation of the seal and the protective layer.

Making the caps.

Production of bridge decking, joints and connection areas

Production of a new passive protection system.

Production of a new railing

Working abutment

After the demolition of the superstructure, the abutments are dismantled to the required height.

Production of the tie anchor in the concrete of the abutments.

Production of new support benches with earth-side spurs

Masonry restoration

Adaptation work in road construction

BW1002 bridge railway road

New superstructure and repair of existing abutments

It is at the bridge to a road overpass, which leads over an electrified railway line. For the first 9 months of construction, the railway line is out of service.

The remaining 9 months must be built under operation.

Inventory from 1951

Superstructure of rolled beams in concrete

Existing width 15,30m, total length 9,90 m.

Planned new building superstructure

Rolled beams in concrete

Width 18,20m, total length 9,90m

Repair of masonry abutments (masonry restoration)

The construction is halfway under traffic.

Work superstructure

Dismantling of the caps with guardrails and guards.

Removing the individual coating layers.

Expansion of the superstructure.

Dismantling of the upper abutment areas.

Production of the new support benches including the rear spurs and wings.

Production of the new superstructure.

Preparation of the seal and the protective layer.

Making the caps.

Production of bridge decking, joints and connection areas

Production of a new passive protection system.

Production of a new railing

Working abutment

After the demolition of the superstructure, the abutments are dismantled to the required height.

Production of the tie anchor in the concrete of the abutments.

Production of new support benches with earth-side spurs

Masonry restoration

Adaptation work in road construction

BW 1010 bridge Viersener Straße; BW 1008 bridge Lindenstraße; BW 1009 bridge Haiderfeldstraße

Brick arch bridge width 15.05 m, total length 32.52 m

It is at the bridge to a road overpass, which leads over an electrified railway line. During construction, the route is out of service.

top:

Half-sided construction under traffic

Dismantling the caps with guardrails and guards.

Removal of the individual coating layers depending on the construction phases.

Expansion of the refill

Repair of the lateral parapet masonry below the carriageway.

Exchange of damaged stones, jointing of the masonry.

Applying a plaster as the basis of the lateral seal.

Applying a bituminous thick coating on the lateral, earth-contacting masonry surfaces.

Installation of the filling.

Production of a concrete slab between the parapet masonry.

Production of a seal and a covering on the concrete slab.

Concreting the new caps.

Production of a new passive protection system.

Production of a new railing

Bottom:

Erection of the dust-proof scaffolding and section-by-section reconstruction of the scaffolding.

Fixing the damaged areas, removal of the damaged stone material.

Grouting the masonry.

Rays of the surface.

Installation of new stones in the damaged areas.

Grouting the stones.

Cleaning the masonry.

Bauwerk BW1008 Lindenstraße, BW1009 Haiderfeldstraße

Masonry arch bridges

Erection of the dust-proof scaffolding and section-by-section reconstruction of the scaffolding.

Fixing the damaged areas, removal of the damaged stone material.

Grouting the masonry.

Rays of the surface.

Installation of new stones in the damaged areas.

Grouting the stones.

Cleaning the masonry.

Download full details as .pdf