As part of a joint occasional award, the city of Hamm announces the construction of the Westtünnn station, including the removal of two level crossings throughout Europe.
To eliminate the two level crossings, the South Feldweg is relocated in trough location under the railway
- production of a railroad overpass structure in the side position with insertion into the end position
- manufacture of troughs made of reinforced concrete
- production of pumping station and rain retention basin including equipment
Start of execution: 27.10.2021
Execution period: 22 months
It is a railway intersection measure.
The planning permit granted by the Federal Railway Office (EBA) is included as an attachment to the tender.
This call for tenders includes as the 1st construction phase:
- the new construction of a railway transfer structure over the laid south dirt road for DB Netz AG
- the new construction of a road tart as part of the railway overpass structure for the city of Hamm
- the new construction of a pumping station in the road troe area for the city of Hamm
- the new construction of road and drainage plants in the railway overpass struction/trough area for the city of Hamm
- drainage systems for the flood ditch in the area P+R plant north side for the city of Hamm
With the construction project, supply lines must also be relocated and reinstalled in sub-areas at the same time. This requires coordination with utilities before the start of construction work.