Shell construction work on the 4th construction phase during the general renovation of a grammar school
Body construction work for the general renovation of a high school.
Gross volume (BRI) BA IV:
(after refurbishment)
BT C: 5.881,50m³
In the course of the demolition and dismantling work (separate LV), the existing buildings will largely be in the shell state
relegated.
Structural change
On the ground floor, the new main entrance of the break hall is being built, which will be made more spacious and representative by a building extension in the north. The break hall opens up through a large glazing both towards the schoolyard in the north and towards the green schoolyard in the south, thus creating a connection between the two outdoor areas.
facade
The façade of the ground floor will be glazed on both sides in the area of the break hall. For this purpose, a large part of the load-bearing outer walls on the south side, as well as the glass blocks on the north side, will be demolished and replaced by mullion-transom facades. The façade of the break hall extension is intended to take up the exposed concrete, which was also used as a design element in the extension of component D. The load-bearing reinforced concrete walls are clad with a suspended exposed concrete façade and thermal insulation in between. The walls continue in the exterior through two opposite exposed concrete wall panels, which border the covered front area of the extension. The canopy of the extension is also designed as a precast exposed concrete element in the same appearance.
Main positions:
- approx. 33.00 m³ demolition of outer walls,
- approx. 3.00 m³ demolition of interior walls
- ca. 50,00 m Betonschneidearbeiten,
- approx. 55.00 m supply/laying sewer pipes,
- approx. 34.00 m³ in-situ concrete
- approx. 9.00 m³ in-situ concrete (exposed concrete)
- approx. 20.00 m³ exposed precast concrete elements
- ca. 16,50 m³ Filigrandecke
- approx. 5.00 Stb-precast lintel windows,
- approx. 40.00 m² brickwork
- approx. 27.00 m steel beam HEB 300
- approx. 28,00m steel columns 140/80mm