Description:

The project includes 3 of the school buildings: the Activity school (AKS) building, the gym building and the main building. The administration building shall not be subject to reconstruction.

The 2 oldest buildings are constructed in the period from 1880 until 1920. The AKS building was constructed in 1995. The total area of the buildings is approx. 9 400 m2.

The project shall be implemented as a general contract with the school partly in operation.

The construction period is from the summer of 2016 until the summer of 2019.

Stage 1: The AKS building and the gym building shall be reconstructed in stage 1 from June 2016 until September 2017. There will be no students in these buildings. At the same time, new technical rooms shall be established in the basement of the main building. In this building the adjacent floors will be in operation. The infrastructure in the school yard shall be renewed during summer holiday 2017.

Stage 2: The main building shall be reconstructed in stage 2 from October 2017 until July 2019. There will be no students in the main building. In this stage simultaneous construction works will be in process in the adjacent park where a new subterranean sports centre shall be constructed. This works shall be published in Doffin at a later date as a separate contract.

The relocation of students and furniture and fittings will taken care of by Municipal Undertaking for Educational Buildings and Property.

The project shall contain the following:

— Installation of new technical systems: ventilation, heating, sanitation, sprinkler, low and high voltage, lifts and accompanying establishment of new technical rooms, new inlets and outlets on roofs/the facades;

— Replacement of all panelled ceiling, new internal doors and glass fields, new fixtures and new surface treatment on all surfaces;

— New infrastructure in the school yard and some upgrading of the school yard;

— New windows in the gym building and some new windows in the AKS and main building;

— New transformer;

— Upgrading and supplementing toilets and changing rooms.

Download full details as .pdf
The Buyer:
Undervisningsbygg Oslo KF [Municipal Undertaking for Educational Buildings and Property]
CPV Code(s):
45000000 - Construction work