Pollutant remediation
Schadstoffsanierung :
Demolition of flat asbestos-containing wall and ceiling coverings (paints and fillers) by means of ultra-high-pressure water processes (approx. 10,850 m2) and dry processes (approx. 1,250 m2) as well as removal of further mineral wool and asbestos sites (e.g. asbestos-cement pipes, flat KMF overlay and KMF pipe sheathing). Demolition of screed, including impact sound insulation. Solidification of the asbestos-containing sludge and the resulting asbestos-containing dusts. Separation and proper disposal of all waste.