This consultation concerns the SANEF Group's 2023, 2024 and 2025 pavement maintenance programme.
Lot 1 - A1 Roye and Arras operating centres - A1 - PR 125 - 135 (direction 1 and 2)The work consists of either:- a reloading of the road surface by the implementation of a rolling layer after milling the old rolling layer.- a structural reinforcement of the pavement by planing the existing road body and the implementation of one or more road layers and a rolling layer
Lot 2 - A1 Roye Operating Centre / Senlis Operations Centre A1 - PR 57 - 78 (direction 1 and 2) and A1 PR 44-57 (direction 1 and 2)The work consists of either:- a reloading of the road surface by the implementation of a rolling layer after milling the old rolling layer.- a structural reinforcement of the pavement by planing the existing road body and the implementation of one or more road layers and a rolling layer
Lot 3 - A16 Beauvais Operations Centre - A16 - PR 94 - 114 - direction 2The work consists of either:- a reloading of the road surface by the implementation of a rolling layer after milling the old rolling layer.- a structural reinforcement of the pavement by planing the existing road body and the implementation of one or more road layers and a rolling layer
Lot 10 : A13 - Morainvilliers and Gaillon operating centres -A13 - PR47 to PR 55 (Direction 1 and 2)The work consists of either:- a reloading of the road surface by the implementation of a rolling layer after milling the old rolling layer.- a structural reinforcement of the pavement by planing the existing road body and the implementation of one or more road layers and a rolling layer
Lot 11 : A13 - Centre de Bourg Achard - A13 - PR 107 to 111 (Direction 2) PR110 to 111 (direction 1 and 2)The work consists of either:- a reloading of the road surface by the implementation of a rolling layer after milling the old rolling layer.- a structural reinforcement of the pavement by planing the existing road body and the implementation of one or more road layers and a rolling layer
Lot 12 : A151 - Yvetot Center - A151 - PR6 to PR 17 (Direction 1)The work consists of either:- a reloading of the road surface by the implementation of a rolling layer after milling the old rolling layer.- a structural reinforcement of the pavement by planing the existing road body and the implementation of one or more road layers and a rolling layer