5.1. The subject of the contract is the modernization of the street surface in the city of Łódź divided into 9 parts.
Part I - task 1.1 - Paradna Street from Obszerna Street to Matek Polskich Street
task 1.2 – Kosynierów Gdyńskich Street from Pryncypalna Street to ChKS and at Rzgowska Street
Part II - task 2.1 - Pushkin Street from Rokicińska Street to Przybyszewskiego Street western roadway with The Invalids Roundabout
Part III - task 3.1 – Matek Polskich Street
Part IV - task 4.1 - hetmańska avenue from Rokicińska Street to Zakładowa Street
Part V - task 5.1 - Brukowa Street from Zbąszyńska Street to St. Teresa Street
Part VI - task 6.1 - St. Teresa Street from Włókniarzy Avenue to Brukowa Street
Part VII - task 7.1 - Nowe Sady Street from Elektronowa Street to the MPK depot
Part VIII - task 8.1 - Krańcowa Street from Biegunowa Street to Konstantynowska Street
Part IX - tasks 9.1 - Ul. Łozowa from Zgierska Street to Kreciej Street
Modernization of Paradna Street and Kosynierów GdyńskichThe subject of the contract is the modernization of Paradna Street and Kosynierów Gdyńskich Street, divided into tasks:
• task 1.1 – Paradna Street from Obszerna Street to Matek Polskich Street
• task 1.2 – Kosynierów Gdyńskich Street from Pryncypalna Street to ChKS and at Rzgowska Street
A detailed description of the subject of the contract can be found in Appendix No. 1 to the SWZ and its annexes, STWiOR and SST. The order was divided into parts. The Contractor may submit a bid for a selected / selected up to four parts of the contract. 5.5. Pursuant to Article 95(1) of the PPL Act, the Contracting Authority shall require the Contractor or subcontractor to employ persons performing the activities indicated by the Ordering Party in the scope of the performance of the contract, if the performance of these activities consists in performing work in the manner specified in Article 22 §1 of the Act of 26 June 1974 – Labour Code (Journal of Laws of 2020, item 1320 i.e.), i.e. three persons for each part of the contract performing work during the execution of the contract in the field of: directing or operating road equipment for each part of the contract. The scope of work of persons performing the activities indicated by the Ordering Party in the scope of contract execution and the method of verifying the employment of these persons and the Ordering Party's right to control the Contractor's compliance with the requirements related to the employment of these persons and sanctions for their non-fulfillment are specified in the Description of the subject of the contract constituting Appendix No. 1 to the SWZ and in the model contract constituting Annex 9 to the SWZ. The Ordering Party shall require the Contractor to lodge a security deposit in the amount of:
- for part I - PLN 68,000.00. in words: sixty-eight thousand 00/100
- for part II – PLN 64,000.00. in words: sixty-four thousand 00/100
- for part III - PLN 56,000.00. in words: fifty-six thousand 00/100
- for part IV – PLN 100,000.00. in words: one hundred thousand 00/100
- for part V – PLN 84,000.00. in words: eighty-four thousand 00/100
- for part VI - PLN 49,000.00. in words: forty-nine thousand 00/100
- for part VII – PLN 42,000.00. in words: forty-two thousand 00/100
- for part VIII - PLN 53,000.00. in words: fifty-three thousand 00/100
- for part IX – PLN 8,000.00. in words: eight thousand 00/100
The contractor whose bid has been selected is obliged to lodge a security for the proper performance of the contract in the amount of 5% of the total gross price specified in the offer for each part of the contract.
The order must be completed within the deadline for:
1) Part I - up to 80 calendar days from the date of handing over the construction site
2) Part II - up to 80 calendar days from the date of handing over the construction site
3) Part III - up to 70 calendar days from the date of handing over the construction site
4) Part IV - up to 80 calendar days from the date of handing over the construction site
5) Part V - up to 80 calendar days from the date of handover of the construction site
6) Part VI - up to 80 calendar days from the date of handover of the construction site
7) Part VII - up to 80 calendar days from the date of handover of the construction site
8) Part VIII - up to 80 calendar days from the date of handing over the construction site
9) Part IX - up to 40 calendar days from the date of handing over the construction site
Modernization of Pushkin Street with the Invalids RoundaboutThe subject of the contract is the modernization of Pushkin Street together with the Invalids Roundabout. A detailed description of the subject of the contract can be found in Appendix No. 1 to the SWZ and its annexes, STWiOR and SST. The order was divided into parts. The Contractor may submit a bid for a selected / selected up to four parts of the contract. Pursuant to Article 95(1) of the PPL Act, the Contracting Authority requires the Contractor or subcontractor to employ persons performing the activities indicated by the Ordering Party in the scope of the contract, if the performance of these activities consists in performing work in the manner specified in Article 22 §1 of the Act of 26 June 1974 – Labour Code (Journal of Laws of 2020, item 1320 i.e.), i.e. three persons for each part of the contract performing work during the execution of the contract in the field of: directing or operating road equipment for each part of the contract. The scope of work of persons performing the activities indicated by the Ordering Party in the scope of contract execution and the method of verifying the employment of these persons and the Ordering Party's right to control the Contractor's compliance with the requirements related to the employment of these persons and sanctions for their non-fulfillment are specified in the Description of the subject of the contract constituting Appendix No. 1 to the SWZ and in the model contract constituting Annex 9 to the SWZ. The Ordering Party shall require the Contractor to lodge a security deposit in the amount of:
- for part I - PLN 68,000.00. in words: sixty-eight thousand 00/100
- for part II – PLN 64,000.00. in words: sixty-four thousand 00/100
- for part III - PLN 56,000.00. in words: fifty-six thousand 00/100
- for part IV – PLN 100,000.00. in words: one hundred thousand 00/100
- for part V – PLN 84,000.00. in words: eighty-four thousand 00/100
- for part VI - PLN 49,000.00. in words: forty-nine thousand 00/100
- for part VII – PLN 42,000.00. in words: forty-two thousand 00/100
- for part VIII - PLN 53,000.00. in words: fifty-three thousand 00/100
- for part IX – PLN 8,000.00. in words: eight thousand 00/100
The contractor whose bid has been selected is obliged to lodge a security for the proper performance of the contract in the amount of 5% of the total gross price specified in the offer for each part of the contract.
The order must be completed within the deadline for:
1) Part I - up to 80 calendar days from the date of handing over the construction site
2) Part II - up to 80 calendar days from the date of handing over the construction site
3) Part III - up to 70 calendar days from the date of handing over the construction site
4) Part IV - up to 80 calendar days from the date of handing over the construction site
5) Part V - up to 80 calendar days from the date of handover of the construction site
6) Part VI - up to 80 calendar days from the date of handover of the construction site
7) Part VII - up to 80 calendar days from the date of handover of the construction site
8) Part VIII - up to 80 calendar days from the date of handing over the construction site
9) Part IX - up to 40 calendar days from the date of handing over the construction site
Modernization of Matek Polskich StreetThe subject of the contract is the modernization of Matek Polskich Street. A detailed description of the subject of the contract can be found in Appendix No. 1 to the SWZ and its annexes, STWiOR and SST. The order was divided into parts. The Contractor may submit a bid for a selected / selected up to four parts of the contract. Pursuant to Article 95(1) of the PPL Act, the Contracting Authority requires the Contractor or subcontractor to employ persons performing the activities indicated by the Ordering Party in the scope of the contract, if the performance of these activities consists in performing work in the manner specified in Article 22 §1 of the Act of 26 June 1974 – Labour Code (Journal of Laws of 2020, item 1320 i.e.), i.e. three persons for each part of the contract performing work during the execution of the contract in the field of: directing or operating road equipment for each part of the contract. The scope of work of persons performing the activities indicated by the Ordering Party in the scope of contract execution and the method of verifying the employment of these persons and the Ordering Party's right to control the Contractor's compliance with the requirements related to the employment of these persons and sanctions for their non-fulfillment are specified in the Description of the subject of the contract constituting Appendix No. 1 to the SWZ and in the model contract constituting Annex 9 to the SWZ. The Ordering Party shall require the Contractor to lodge a security deposit in the amount of:
- for part I - PLN 68,000.00. in words: sixty-eight thousand 00/100
- for part II – PLN 64,000.00. in words: sixty-four thousand 00/100
- for part III - PLN 56,000.00. in words: fifty-six thousand 00/100
- for part IV – PLN 100,000.00. in words: one hundred thousand 00/100
- for part V – PLN 84,000.00. in words: eighty-four thousand 00/100
- for part VI - PLN 49,000.00. in words: forty-nine thousand 00/100
- for part VII – PLN 42,000.00. in words: forty-two thousand 00/100
- for part VIII - PLN 53,000.00. in words: fifty-three thousand 00/100
- for part IX – PLN 8,000.00. in words: eight thousand 00/100
The contractor whose bid has been selected is obliged to lodge a security for the proper performance of the contract in the amount of 5% of the total gross price specified in the offer for each part of the contract.
The order must be completed within the deadline for:
1) Part I - up to 80 calendar days from the date of handing over the construction site
2) Part II - up to 80 calendar days from the date of handing over the construction site
3) Part III - up to 70 calendar days from the date of handing over the construction site
4) Part IV - up to 80 calendar days from the date of handing over the construction site
5) Part V - up to 80 calendar days from the date of handover of the construction site
6) Part VI - up to 80 calendar days from the date of handover of the construction site
7) Part VII - up to 80 calendar days from the date of handover of the construction site
8) Part VIII - up to 80 calendar days from the date of handing over the construction site
9) Part IX - up to 40 calendar days from the date of handing over the construction site
Modernization of Hetmanska StreetThe subject of the contract is the modernization of Hetmańska Street. A detailed description of the subject of the contract can be found in Appendix No. 1 to the SWZ and its annexes, STWiOR and SST. The order was divided into parts. The Contractor may submit a bid for a selected / selected up to four parts of the contract. Pursuant to Article 95(1) of the PPL Act, the Contracting Authority requires the Contractor or subcontractor to employ persons performing the activities indicated by the Ordering Party in the scope of the contract, if the performance of these activities consists in performing work in the manner specified in Article 22 §1 of the Act of 26 June 1974 – Labour Code (Journal of Laws of 2020, item 1320 i.e.), i.e. three persons for each part of the contract performing work during the execution of the contract in the field of: directing or operating road equipment for each part of the contract. The scope of work of persons performing the activities indicated by the Ordering Party in the scope of contract execution and the method of verifying the employment of these persons and the Ordering Party's right to control the Contractor's compliance with the requirements related to the employment of these persons and sanctions for their non-fulfillment are specified in the Description of the subject of the contract constituting Appendix No. 1 to the SWZ and in the model contract constituting Annex 9 to the SWZ. The Ordering Party shall require the Contractor to lodge a security deposit in the amount of:
- for part I - PLN 68,000.00. in words: sixty-eight thousand 00/100
- for part II – PLN 64,000.00. in words: sixty-four thousand 00/100
- for part III - PLN 56,000.00. in words: fifty-six thousand 00/100
- for part IV – PLN 100,000.00. in words: one hundred thousand 00/100
- for part V – PLN 84,000.00. in words: eighty-four thousand 00/100
- for part VI - PLN 49,000.00. in words: forty-nine thousand 00/100
- for part VII – PLN 42,000.00. in words: forty-two thousand 00/100
- for part VIII - PLN 53,000.00. in words: fifty-three thousand 00/100
- for part IX – PLN 8,000.00. in words: eight thousand 00/100
The contractor whose bid has been selected is obliged to lodge a security for the proper performance of the contract in the amount of 5% of the total gross price specified in the offer for each part of the contract.
The order must be completed within the deadline for:
1) Part I - up to 80 calendar days from the date of handing over the construction site
2) Part II - up to 80 calendar days from the date of handing over the construction site
3) Part III - up to 70 calendar days from the date of handing over the construction site
4) Part IV - up to 80 calendar days from the date of handing over the construction site
5) Part V - up to 80 calendar days from the date of handover of the construction site
6) Part VI - up to 80 calendar days from the date of handover of the construction site
7) Part VII - up to 80 calendar days from the date of handover of the construction site
8) Part VIII - up to 80 calendar days from the date of handing over the construction site
9) Part IX - up to 40 calendar days from the date of handing over the construction site
Modernization of Brukowa StreetThe subject of the contract is the modernization of Brukowa Street. A detailed description of the subject of the contract can be found in Appendix No. 1 to the SWZ and its annexes, STWiOR and SST. The order was divided into parts. The Contractor may submit a bid for a selected / selected up to four parts of the contract. Pursuant to Article 95(1) of the PPL Act, the Contracting Authority requires the Contractor or subcontractor to employ persons performing the activities indicated by the Ordering Party in the scope of the contract, if the performance of these activities consists in performing work in the manner specified in Article 22 §1 of the Act of 26 June 1974 – Labour Code (Journal of Laws of 2020, item 1320 i.e.), i.e. three persons for each part of the contract performing work during the execution of the contract in the field of: directing or operating road equipment for each part of the contract. The scope of work of persons performing the activities indicated by the Ordering Party in the scope of contract execution and the method of verifying the employment of these persons and the Ordering Party's right to control the Contractor's compliance with the requirements related to the employment of these persons and sanctions for their non-fulfillment are specified in the Description of the subject of the contract constituting Appendix No. 1 to the SWZ and in the model contract constituting Annex 9 to the SWZ. The Ordering Party shall require the Contractor to lodge a security deposit in the amount of:
- for part I - PLN 68,000.00. in words: sixty-eight thousand 00/100
- for part II – PLN 64,000.00. in words: sixty-four thousand 00/100
- for part III - PLN 56,000.00. in words: fifty-six thousand 00/100
- for part IV – PLN 100,000.00. in words: one hundred thousand 00/100
- for part V – PLN 84,000.00. in words: eighty-four thousand 00/100
- for part VI - PLN 49,000.00. in words: forty-nine thousand 00/100
- for part VII – PLN 42,000.00. in words: forty-two thousand 00/100
- for part VIII - PLN 53,000.00. in words: fifty-three thousand 00/100
- for part IX – PLN 8,000.00. in words: eight thousand 00/100
The contractor whose bid has been selected is obliged to lodge a security for the proper performance of the contract in the amount of 5% of the total gross price specified in the offer for each part of the contract.
The order must be completed within the deadline for:
1) Part I - up to 80 calendar days from the date of handing over the construction site
2) Part II - up to 80 calendar days from the date of handing over the construction site
3) Part III - up to 70 calendar days from the date of handing over the construction site
4) Part IV - up to 80 calendar days from the date of handing over the construction site
5) Part V - up to 80 calendar days from the date of handover of the construction site
6) Part VI - up to 80 calendar days from the date of handover of the construction site
7) Part VII - up to 80 calendar days from the date of handover of the construction site
8) Part VIII - up to 80 calendar days from the date of handing over the construction site
9) Part IX - up to 40 calendar days from the date of handing over the construction site
Modernization of St. Teresa StreetThe subject of the contract is the modernization of St. Teresa Street. A detailed description of the subject of the contract can be found in Appendix No. 1 to the SWZ and its annexes, STWiOR and SST. The order was divided into parts. The Contractor may submit a bid for a selected / selected up to four parts of the contract. Pursuant to Article 95(1) of the PPL Act, the Contracting Authority requires the Contractor or subcontractor to employ persons performing the activities indicated by the Ordering Party in the scope of the contract, if the performance of these activities consists in performing work in the manner specified in Article 22 §1 of the Act of 26 June 1974 – Labour Code (Journal of Laws of 2020, item 1320 i.e.), i.e. three persons for each part of the contract performing work during the execution of the contract in the field of: directing or operating road equipment for each part of the contract. The scope of work of persons performing the activities indicated by the Ordering Party in the scope of contract execution and the method of verifying the employment of these persons and the Ordering Party's right to control the Contractor's compliance with the requirements related to the employment of these persons and sanctions for their non-fulfillment are specified in the Description of the subject of the contract constituting Appendix No. 1 to the SWZ and in the model contract constituting Annex 9 to the SWZ. The Ordering Party shall require the Contractor to lodge a security deposit in the amount of:
- for part I - PLN 68,000.00. in words: sixty-eight thousand 00/100
- for part II – PLN 64,000.00. in words: sixty-four thousand 00/100
- for part III - PLN 56,000.00. in words: fifty-six thousand 00/100
- for part IV – PLN 100,000.00. in words: one hundred thousand 00/100
- for part V – PLN 84,000.00. in words: eighty-four thousand 00/100
- for part VI - PLN 49,000.00. in words: forty-nine thousand 00/100
- for part VII – PLN 42,000.00. in words: forty-two thousand 00/100
- for part VIII - PLN 53,000.00. in words: fifty-three thousand 00/100
- for part IX – PLN 8,000.00. in words: eight thousand 00/100
The contractor whose bid has been selected is obliged to lodge a security for the proper performance of the contract in the amount of 5% of the total gross price specified in the offer for each part of the contract.
The order must be completed within the deadline for:
1) Part I - up to 80 calendar days from the date of handing over the construction site
2) Part II - up to 80 calendar days from the date of handing over the construction site
3) Part III - up to 70 calendar days from the date of handing over the construction site
4) Part IV - up to 80 calendar days from the date of handing over the construction site
5) Part V - up to 80 calendar days from the date of handover of the construction site
6) Part VI - up to 80 calendar days from the date of handover of the construction site
7) Part VII - up to 80 calendar days from the date of handover of the construction site
8) Part VIII - up to 80 calendar days from the date of handing over the construction site
9) Part IX - up to 40 calendar days from the date of handing over the construction site
Modernization of Nowe Sady StreetThe subject of the contract is the modernization of Nowe Sady Street. A detailed description of the subject of the contract can be found in Appendix No. 1 to the SWZ and its annexes, STWiOR and SST. The order was divided into parts. The Contractor may submit a bid for a selected / selected up to four parts of the contract. Pursuant to Article 95(1) of the PPL Act, the Contracting Authority requires the Contractor or subcontractor to employ persons performing the activities indicated by the Ordering Party in the scope of the contract, if the performance of these activities consists in performing work in the manner specified in Article 22 §1 of the Act of 26 June 1974 – Labour Code (Journal of Laws of 2020, item 1320 i.e.), i.e. three persons for each part of the contract performing work during the execution of the contract in the field of: directing or operating road equipment for each part of the contract. The scope of work of persons performing the activities indicated by the Ordering Party in the scope of contract execution and the method of verifying the employment of these persons and the Ordering Party's right to control the Contractor's compliance with the requirements related to the employment of these persons and sanctions for their non-fulfillment are specified in the Description of the subject of the contract constituting Appendix No. 1 to the SWZ and in the model contract constituting Annex 9 to the SWZ. The Ordering Party shall require the Contractor to lodge a security deposit in the amount of:
- for part I - PLN 68,000.00. in words: sixty-eight thousand 00/100
- for part II – PLN 64,000.00. in words: sixty-four thousand 00/100
- for part III - PLN 56,000.00. in words: fifty-six thousand 00/100
- for part IV – PLN 100,000.00. in words: one hundred thousand 00/100
- for part V – PLN 84,000.00. in words: eighty-four thousand 00/100
- for part VI - PLN 49,000.00. in words: forty-nine thousand 00/100
- for part VII – PLN 42,000.00. in words: forty-two thousand 00/100
- for part VIII - PLN 53,000.00. in words: fifty-three thousand 00/100
- for part IX – PLN 8,000.00. in words: eight thousand 00/100
The contractor whose bid has been selected is obliged to lodge a security for the proper performance of the contract in the amount of 5% of the total gross price specified in the offer for each part of the contract.
The order must be completed within the deadline for:
1) Part I - up to 80 calendar days from the date of handing over the construction site
2) Part II - up to 80 calendar days from the date of handing over the construction site
3) Part III - up to 70 calendar days from the date of handing over the construction site
4) Part IV - up to 80 calendar days from the date of handing over the construction site
5) Part V - up to 80 calendar days from the date of handover of the construction site
6) Part VI - up to 80 calendar days from the date of handover of the construction site
7) Part VII - up to 80 calendar days from the date of handover of the construction site
8) Part VIII - up to 80 calendar days from the date of handing over the construction site
9) Part IX - up to 40 calendar days from the date of handing over the construction site
Modernization of Krańcowa StreetThe subject of the contract is the modernization of Krańcowa Street. A detailed description of the subject of the contract can be found in Appendix No. 1 to the SWZ and its annexes, STWiOR and SST. The order was divided into parts. The Contractor may submit a bid for a selected / selected up to four parts of the contract. Pursuant to Article 95(1) of the PPL Act, the Contracting Authority requires the Contractor or subcontractor to employ persons performing the activities indicated by the Ordering Party in the scope of the contract, if the performance of these activities consists in performing work in the manner specified in Article 22 §1 of the Act of 26 June 1974 – Labour Code (Journal of Laws of 2020, item 1320 i.e.), i.e. three persons for each part of the contract performing work during the execution of the contract in the field of: directing or operating road equipment for each part of the contract. The scope of work of persons performing the activities indicated by the Ordering Party in the scope of contract execution and the method of verifying the employment of these persons and the Ordering Party's right to control the Contractor's compliance with the requirements related to the employment of these persons and sanctions for their non-fulfillment are specified in the Description of the subject of the contract constituting Appendix No. 1 to the SWZ and in the model contract constituting Annex 9 to the SWZ. The Ordering Party shall require the Contractor to lodge a security deposit in the amount of:
- for part I - PLN 68,000.00. in words: sixty-eight thousand 00/100
- for part II – PLN 64,000.00. in words: sixty-four thousand 00/100
- for part III - PLN 56,000.00. in words: fifty-six thousand 00/100
- for part IV – PLN 100,000.00. in words: one hundred thousand 00/100
- for part V – PLN 84,000.00. in words: eighty-four thousand 00/100
- for part VI - PLN 49,000.00. in words: forty-nine thousand 00/100
- for part VII – PLN 42,000.00. in words: forty-two thousand 00/100
- for part VIII - PLN 53,000.00. in words: fifty-three thousand 00/100
- for part IX – PLN 8,000.00. in words: eight thousand 00/100
The contractor whose bid has been selected is obliged to lodge a security for the proper performance of the contract in the amount of 5% of the total gross price specified in the offer for each part of the contract.
The order must be completed within the deadline for:
1) Part I - up to 80 calendar days from the date of handing over the construction site
2) Part II - up to 80 calendar days from the date of handing over the construction site
3) Part III - up to 70 calendar days from the date of handing over the construction site
4) Part IV - up to 80 calendar days from the date of handing over the construction site
5) Part V - up to 80 calendar days from the date of handover of the construction site
6) Part VI - up to 80 calendar days from the date of handover of the construction site
7) Part VII - up to 80 calendar days from the date of handover of the construction site
8) Part VIII - up to 80 calendar days from the date of handing over the construction site
9) Part IX - up to 40 calendar days from the date of handing over the construction site
Modernization of Łozowa StreetThe subject of the contract is the modernization of Łozowa Street. A detailed description of the subject of the contract can be found in Appendix No. 1 to the SWZ and its annexes, STWiOR and SST. The order was divided into parts. The Contractor may submit a bid for a selected / selected up to four parts of the contract. Pursuant to Article 95(1) of the PPL Act, the Contracting Authority requires the Contractor or subcontractor to employ persons performing the activities indicated by the Ordering Party in the scope of the contract, if the performance of these activities consists in performing work in the manner specified in Article 22 §1 of the Act of 26 June 1974 – Labour Code (Journal of Laws of 2020, item 1320 i.e.), i.e. three persons for each part of the contract performing work during the execution of the contract in the field of: directing or operating road equipment for each part of the contract. The scope of work of persons performing the activities indicated by the Ordering Party in the scope of contract execution and the method of verifying the employment of these persons and the Ordering Party's right to control the Contractor's compliance with the requirements related to the employment of these persons and sanctions for their non-fulfillment are specified in the Description of the subject of the contract constituting Appendix No. 1 to the SWZ and in the model contract constituting Annex 9 to the SWZ. The Ordering Party shall require the Contractor to lodge a security deposit in the amount of:
- for part I - PLN 68,000.00. in words: sixty-eight thousand 00/100
- for part II – PLN 64,000.00. in words: sixty-four thousand 00/100
- for part III - PLN 56,000.00. in words: fifty-six thousand 00/100
- for part IV – PLN 100,000.00. in words: one hundred thousand 00/100
- for part V – PLN 84,000.00. in words: eighty-four thousand 00/100
- for part VI - PLN 49,000.00. in words: forty-nine thousand 00/100
- for part VII – PLN 42,000.00. in words: forty-two thousand 00/100
- for part VIII - PLN 53,000.00. in words: fifty-three thousand 00/100
- for part IX – PLN 8,000.00. in words: eight thousand 00/100
The contractor whose bid has been selected is obliged to lodge a security for the proper performance of the contract in the amount of 5% of the total gross price specified in the offer for each part of the contract.
The order must be completed within the deadline for:
1) Part I - up to 80 calendar days from the date of handing over the construction site
2) Part II - up to 80 calendar days from the date of handing over the construction site
3) Part III - up to 70 calendar days from the date of handing over the construction site
4) Part IV - up to 80 calendar days from the date of handing over the construction site
5) Part V - up to 80 calendar days from the date of handover of the construction site
6) Part VI - up to 80 calendar days from the date of handover of the construction site
7) Part VII - up to 80 calendar days from the date of handover of the construction site
8) Part VIII - up to 80 calendar days from the date of handing over the construction site
9) Part IX - up to 40 calendar days from the date of handing over the construction site