Supply of electricity in 2019 for the Municipality of Gdynia and its organizational units and other Municipalities, including those operating in partnership: the Metropolitan Forum of Heads, Mayors, Presidents and Starostes - NORDA and other municipalities and poviats, as well as with organizational units, legal entities, cultural institutions and municipal companies of these Municipalities and Poviats, Naval Academy in Gdynia.
Supply of electricity to premises and facilities1. Number of measuring systems accounting for electricity consumed 29 pcs.
2. A detailed description of the collection points (PPE) the Employer has included in Annex 1a to the ToR.
3. Estimated electricity consumption over the duration of the contract (+/- 10%) 16,096.93 MWh, of which:
Zone I 7 886.13 MWh
Zone II 1 962.74 MWh
Zone III 6 248.06 MWh
The above data is indicative. The contractor should take into account possible fluctuations in electricity consumption.
4. Deliveries will take place from 1/1/2019 to 31/12/2019, with the proviso that the details regarding delivery dates (start and end) in relation to individual collection points are described in Annex 1a to the ToR, column "Delivery period ".
Supply of electricity for the purposes of road lighting and traffic lights1. Number of measuring systems accounting for consumed electricity 1 244 pcs.
2. A detailed description of the collection points (PPE) has been placed by the Employer in Annex 1b to the ToR.
3. Estimated electricity consumption during the contract period (+/- 10%) 13,982.61 MWh, of which:
Zone I 3 835.25 MWh
Zone II 10 147.36 MWh
Zone III 0.00 MWh
The above data is indicative. The contractor should take into account possible fluctuations in electricity consumption.
4. Deliveries will take place from 1/11/2019 to 31/12/2019 with the proviso that the details regarding delivery dates (start and end) in relation to individual collection points are described in Annex No. 1b to the Terms of Reference, column "Delivery period ".