General construction work for pipelines | Tenderlake

General construction work for pipelines

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
09 December 2022
Closing Date:
13 January 2023
Location(s):
PL911 Miasto Warszawa (PL Poland/POLSKA)
Description:
Execution of construction works in the scope of reconstruction and construction of the following sections of the heating network (s.c.): section from C29/L11 to Puławska 230 (Niedźwiedzia / Wita Stwosza) - SC II 60.

The subject of the Contract is the execution of construction works in the field of reconstruction and construction of the following sections of the heating network (s.c.): section from C29/L11 to Puławska 230 (Niedźwiedzia / Wita Stwosza) - SC II 60; as part of the task: Reconstruction of 14.06 km of the heating network in Warsaw - execution of construction works for sections of the network with registration number: SC II 1; SC II 2; SC II 14; SC II 16; SC II 17; SC II 21; SC II 31; SC II 32; SC II 39; SC II 44; SC II 45; SC II 50; SC II 59; SC II 60; SC II 61; SC II 63; SC II 64; SC II 65; SC II 66; SC II 67; SC II 68; SC II 71; SC II 72; SC II 73; SC II 74; SC II 76; SC II 77; SC II 78; SC II 79; SC II 81; SC II 82; SC II 84; SC II 85; SC II 86; SC II 87; SC II 89; SC II 48; SC II 4; SC II 94; SC II 95; as part of the project: "Modernization of the Warsaw district heating network in the Capital City of Warsaw in order to reduce carbon dioxide emissions and improve energy efficiency - stage II" POIS.01.05.00-00-0040/16; under the Operational Programme Infrastructure and Environment 2014-2020, Priority Axis I Reduction of emissions of the economy, Measure 1.5 Effective distribution of heat and cold.

A detailed description of the subject of the contract includes:

1. project documentation and formal and legal documentation,

2. technical specifications for the performance and reception of construction works

- forming part III of SWZ.

The subject of the Contract is the execution of construction works in the field of reconstruction and construction of the following sections of the heating network (s.c.): section from C29/L11 to Puławska 230 (Niedźwiedzia / Wita Stwosza) - SC II 60; as part of the task: Reconstruction of 14.06 km of the heating network in Warsaw - execution of construction works for sections of the network with registration number: SC II 1; SC II 2; SC II 14; SC II 16; SC II 17; SC II 21; SC II 31; SC II 32; SC II 39; SC II 44; SC II 45; SC II 50; SC II 59; SC II 60; SC II 61; SC II 63; SC II 64; SC II 65; SC II 66; SC II 67; SC II 68; SC II 71; SC II 72; SC II 73; SC II 74; SC II 76; SC II 77; SC II 78; SC II 79; SC II 81; SC II 82; SC II 84; SC II 85; SC II 86; SC II 87; SC II 89; SC II 48; SC II 4; SC II 94; SC II 95; as part of the project: "Modernization of the Warsaw district heating network in the Capital City of Warsaw in order to reduce carbon dioxide emissions and improve energy efficiency - stage II" POIS.01.05.00-00-0040/16; under the Operational Programme Infrastructure and Environment 2014-2020, Priority Axis I Reduction of emissions of the economy, Measure 1.5 Effective distribution of heat and cold.

A detailed description of the subject of the contract includes:

1. project documentation and formal and legal documentation,

2. technical specifications for the performance and reception of construction works

- forming part III of SWZ.

Download full details as .pdf
The Buyer:
Veolia Energia Warszawa S.A.
CPV Code(s):
45231100 - General construction work for pipelines