Feuchtwangen University of Applied Sciences - 2nd construction phase - New construction of the classroom building
The research hall of the university in Feuchtwangen is to be extended by a classroom building with lecture hall, office and seminar rooms, necessary sanitary facilities and traffic areas.
HEATING INSTALLATION - Feuchtwangen University of Applied Sciences - 2nd BA - New construction of lecture hall building: 1x sole heat pump 45kW incl. control control cabinet;
1x relocation to extension of the existing floor heat pump 29kW incl. connection;
27x solar-air collector;
1x hydraulic and control interconnection of the heat pumps as a cascade with existing ice storage;
3x regulated heating circuit, 1x unregulated heating circuit DN 20 -DN 80;
approx. 700 m of steel pipe and fittings DN 15 -DN 50;
approx. 65 m PEx pipe and fittings DN 75 -DN 110;
approx. 3 steel tubular radiators with integrated valve;