Extension, conversion and renovation of the List property in Schaufling - drywall construction work
Trockenbauarbeiten:
Start of construction of Bürgersaal for drywall: 22.05.2023 (21st week 2023)
Completion of installation levels at Bürgersaal: 23.06.2023 (25th week 2023)
Start of planking and ceiling work Bürgersaal from 14.08.2023 (33rd week 2023)
Completion of the Bürgersaal: 20.10.2023 (42nd week 2023)
Start of construction of citizen rooms/guest house for drywall: 07.08.2023 (32nd week 2023)
Completion of installation levels for public rooms/guest house: 25.08.2023 (34th week 2023)
Start of planking and ceiling work in public rooms/guest house from 09.10.2023 (41st week 2023)
Completion of citizen rooms/guest house: 10.02.2024 (06. KW 2024)