Finsing Primary and Middle School; Extension of the west wing
VE 403 - Heizungsarbeiten
Heating work:
- Heat generation: connection to existing central heating system (without transfer station)
- 3 heating circuits (FBH, ventilation roof, ventilation kitchen)
- 1 system separator for heating circuit roof (frost protection)
- Heating pipe stainless steel, DN12-DN50 approx. 550m (partly visual installations),
of which approx. 80m installed outdoors on flat roof (connection ventilation unit)
- Insulation for all pipes, outdoors with sheet metal jacket, in the building
Viewing areas PVC sheathed
- Fire protection measures approx. 30 pcs.
- Underfloor heating approx. 11,360 m², insulation laid on site
- Distribution cabinets FBH 17 pcs.