Sanitary and fire extinguishing systems at the German Architecture Museum in Frankfurt
The construction project is
Replacement of the entire drinking water network, sanitary facilities and fire extinguishing network including wall hydrants
Storey: 5 full floors
The following services are carried out:
Sanitary facility:
- 170 m stainless steel piping including pipe insulation from DN 15 to DN 25
- 70 m stainless steel piping including pipe insulation from DN 32 to DN 40
- 46 m drain pipes from DN 50 to DN 100
- 22 sanitary objects (WC, WC, etc.)
- 1 piece disassembly work
Fire extinguishing system (dry)
- 4 fire extinguisher wall hydrant
- 164m carbon steel pipe DN 50-80