Description:
Extension of wastewater treatment plant I in the industrial park Schwarze Pumpe; Lot 5 - anaerobic reactor

The ABA I is a plant for the combined treatment of paper wastewater (Annex 28 AbwV), other industrial wastewater (Annex 22 AbwV) and sanitary wastewater (Annex 1 AbwV), consisting of a mechanical pre-cleaning, anaerobic cleaning and an aerobic cleaning. The cooling takes place before the biological cleaning. The capacity for the paper waste water 6 240 m 3 / d and 32 000 kg COD / d (measured at the inlet of the anaerobic stage). The capacity for sanitary and other industrial wastewater is 1 085 m 3 / d and 1 150 kg COD / d. The mechanical and biological sludge of the plant increase after thickening of the paper mill. The plant is to be expanded to provide redundancy capacity for inspection and maintenance.

Planning, delivery and installation services for the expansion of the wastewater treatment plant ABA I, as well as expansion of the infrastructure development at the industrial site Schwarze Pumpe / extension old site IG Spreewitz.

In the anaerobic reactors, pre-acidified wastewater from the hydrolysis tank is treated anaerobically. In the ABA I are currently in the anaerobic stage 4 containers in a row. 3 of these containers are used as anaerobic reactors. The fourth container (the easternmost) is of identical design, but so far has no internals (separator, inflow, heavy sludge, etc.). In the course of this call for tenders (lot 5), this vessel is to be converted into a fourth, fully functional anaerobic reactor ("anaerobic reactor 4 expansion"). These include construction, design, delivery and installation of the required system components. It is necessary to make a static proof of the container and, if necessary, make adjustments to the container to achieve the static requirements and allow for it. Commissioning of the dismantled anaerobic reactor 4 must be supported and included by the contractor. After commissioning, the proof of performance and the acceptance by the client are carried out.

Furthermore, the entire hydraulics of the anaerobic stage should be demonstrated ("Anaerobic Stage Engineering Package"). Task is the design of the complete system anaerobic stage including complete hydraulics on the basis of a factory planning by the planner M Consult. The Contractor shall check the hydraulic design of the complete system from inlet anaerobic stage via conditioning - pellet capture - anaerobic reactors 1-4 including recirculation up to the effluent to the activated sludge tanks. If deviations occur, these are to be evaluated, an alternative concept must be proposed and the additional expenses must be calculated.

In the context of the extension of ABA I - lot 5 "Expansion of anaerobic reactor 4", the following main services are required:

- engineering package anaerobic stage,

- expansion of anaerobic reactor 4,

- Further work anaerobic reactor 4.

Download full details as .pdf
The Buyer:
Zweckverband Industriepark Schwarze Pumpe (ZV ISP) vertreten durch die ASG Spremberg GmbH als Treuhänder
CPV Code(s):
42996000 - Machinery for the treatment of sewage
45232421 - Sewage treatment works
45252127 - Wastewater treatment plant construction work
45252130 - Sewage plant equipment