The bill of quantities is divided into the following sections:
1. Section 4.BA New building / component L 2. Section 3.BA Reorganization of maintenance / 2nd partial building measure 440/450 Electrotechnical installations
The hospital intends to carry out the construction project 4.BA/3.BA/2 while maintaining the Brankenhaus operation. Part construction project.
The Elt.-supply of the final distributions takes place from the vorh. Building main distribution (GHV) in the UG BT-E.
The line network is separated according to AV and SV gem. to build up the VDE regulations.
The final distributors (separate cabinets for AV and SV) are supplied star-shaped from the GHV.
Assigned to each EV is an equipotential bonding bar for the distribution area concerned.
Equipotential bonding rails must be provided for the ZPA in AG 1 and AG 2 rooms.
The cable routes in the escape and rescue routes are enclosed with an I30 panel. Lines, which serve exclusively for the supply of the escape and rescue routes, are laid open.
For the SV supply of the EVs, the cable routes in E90 must be carried out.