New construction of an office building with 5 rising floors, partial basement according to DGNB Gold certification requirements. The building cubature as a rectangular volume with two courtyards of different sizes has an edge length of approx. 86m x 41m. The gross floor area is approx. 15,709m2, the partial basement approx. 1,645m2. Building height: 20.20 m OK Attica
Heating and cooling, insulation work, space heating surfaces, convection cooling units
approx. 2,000m heating cables made of steel pipe including thermal insulation and fittings
approx. 3,200m heating cables made of stainless steel pipe including thermal insulation and fittings
approx. 1,500m heating cables made of metal composite pipe including thermal insulation and fittings
approx. 1,150 pieces of shut-off and control valves
approx. 2,080 pieces of metal heating and cooling sails from 1.0x0.6m to 3.0x0.98m
13 pcs heating pumps
approx. 110 pieces of panel radiators
approx. 840m of refrigeration pipes made of steel pipe including thermal insulation and fittings
approx. 6,950m of refrigeration pipes made of stainless steel pipe including thermal insulation and fittings
approx. 1,150 pieces of shut-off and control valves
11 refrigeration pumps
36 pieces of circulating air cooling units
Start of W+M planning: January 2024
Start of installation of routes: April 2024
Start Rohinstallation: June 2024
Start of installation of heating/cooling sails: February 2025
End of installation: July 2025
End of trial operation: November 2025