L3011, interim construction without cycle path incl. replacement of a retaining wall on the Mühlgraben near Hofheim-Lorsbach, ceiling renovation of the L3011 to approx. 2km length, expansion of the Heinrichsweg to approx. 2km length, as well as the associated traffic safety, marking and protection equipment work
ca. 1.000m Ortbetonbohrpfahl
approx. 1000m³ reinforced concrete
approx. 3.000m² new road construction
approx. 2km (7.000m²) Upgrading forest path
ca. 2km (13.000m²) Deckensanierung
ca. 330m Stahlgeländer
Stauraumkanal + Schachtbauwerke