New construction of a four-school integrated comprehensive school - electrical installation work.
Execution of the electrical installation work for the new construction of a four-level integrated comprehensive school with assembly hall, 2-field sports hall, promotion center and official residence.
- BGF approx .: 14 500 m²,
- BRI approx .: 62 450 m³.
The works essentially include:
- 1 pc CPS central battery system,
- 1 pc low voltage main distributor with power supply measurement,
- approx. 90,000 m of cables / lines without functional integrity,
- approx. 9,000 m of cables / lines with functional integrity,
- about 950 m. Cable tray,
- approx. 9,500 pieces of collective holders,
- approx. 1 800 St. switches and sockets,
- approx. 20 pc. Subdistributor,
- about 1 800 St. lamps,
- approx. 500 St. escape route and emergency lights,
- 3 pc video intercoms,
- 1 hour announcement and break-time equipment,
- approx. 270 St speaker 100 V technology,
- 1 fire alarm system,
- approx. 1 100 pcs. Automatic and non-automatic fire detectors,
- approx. 400 St. KNX components for blinds and lighting control,
- approx. 500 pc. EDP junction boxes,
- approx. 35,000 m data cable.