Dismantling Rathaus-Center of the City of Ludwigshafen - Award of construction site logistics
Bauprojektgesellschaft Ludwigshafen mbh (BPG), as the municipal company of the city of Ludwigshafen am Rhein, is planning the dismantling of the Rathaus-Center. The dismantling is to be completed by the end of 2025, as this is a direct prerequisite for the subsequent dismantling and new construction of the elevated road (B44).
The building complex consists of a multi-storey shopping centre and a high-rise building with 17 floors as well as a multi-storey, integrated multi-storey car park. The multi-storey car park is connected to the nearby federal highway B44, which leads to
Part also runs above the northern wing of the mall. Furthermore, several railway lines run in Baufeld and below the Rathaus-Center, where there is also a stop. The tracks must be protected and used during the
Dismantling in active use.
Building height: 1977 to 1979 Building height Tower: approx. 68 m above the site Building height Center: approx. 13 m above ground Basement: at approx. - 4.60 m Constructed room: approx. 315,000 cbm Interior, load-bearing walls: masonry, reinforced concrete, stb supports Exterior facade: Curtain facade, post transom construction roofs: flat roofs, extensively greened and walkable Groundwater level: According to Geoportal Rhineland-Palatinate in accordance with Geoportal 4.88 m below GOF
At the present time, a feasibility study and approval for dismantling as well as the early start of construction have been obtained. Since mid-2022, early measures have been planned and put out to tender, further EU tenders for the
Construction work has been carried out, which is to be awarded at the beginning of 2023. Parallel to the EU-wide invitation to tender for the construction measures, early measures such as BE installation, media separation, early renovation measures, removal of green roofs and roof superstructures are in the execution.
Technical work, updating of the construction site logistics concept as well as construction logistics phases, plans or detailed plans according to the requirements. The service to be provided results in detail from the appendix Performance profile
(Appendix 1).