St. Marien and Annastifts Hospital
Future project human + health
Adding component G and converting component F
VE_503 Lifting Systems - Rainwater
2 pcs. rainwater lifting system as a double pump system
Deliver 2 inlet buildings (installation takes place on site)
Approx. 100 running metre pressure line between lifting station and transfer bay
Two sections, supply the pressure line and lay it in on-site trench
2 pcs. electrotechnical control for lifting stations
2 pcs. outdoor distribution cabinet for electrotechn. controller
Pressure lines leak tests
documentation
maintenance services
Start of construction: probably 24/25 week 2022
Completion:
Contractual intermediate periods:
Completion and commissioning of the South lifting plant until late. 23.09.2022 Main entrance north: shaft construction, distributor, pressure line until late. 10/11/2022
The work is divided into several sections/sub-areas.
Overall completion: end of week 13 2024 at the latest