Explosive ordnance detection and clearance work as well as the construction of a construction road on several construction sites in the area of the planned tunnel construction west.
Preferred KME WestExplosive ordnance detection and clearance work:
- 42,000 m
- 130,000 m exploratory drilling;
- 12,500 m
Create construction road:
- Install 2,500 t of coarse impact as an improvement to the subsoil;
- 3 850 m
- 3,900 m
- 3 500 m
- 3 500 m